13029 N GLADSTONE AVE 91342
Certificate Information: 13029 N GLADSTONE AVE 91342
- Application / Permit
- 22014-20000-06049
- Plan Check / Job No.
- B22VN18290
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 5'9" X 14'6" ADDITION TO FRONT OF SFD. (N) 10' X 10' PORCH ADDITION. CONVERT 20'6" X 26' (E) CARPORT TO SFD FAMING ROOM. (N) 20' X 21' ATTACHED 2-CAR GARAGE. REMODEL OF SFD TO CONVERT LIVING ROOM TO MASTER BEDROOM W/ BATHROOM, REMODEL BATHROOMS, RELOCATE KITCHEN / LIVING ROOM / DINING ROOM. ALL WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 7/3/2024
- Issuing Office
- Current Status
- Issued on 7/3/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/21/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 2/13/2024 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 6/18/2024 | DANIEL ABRAMYAN |
| Plan Check Approved | 6/25/2024 | MADISON O'DELL |
| No Progress | 6/25/2024 | MADISON O'DELL |
| Plan Check Approved | 6/25/2024 | MADISON O'DELL |
| Issued | 7/3/2024 | APPLICANT |
Permit Application Clearance Information
| Private street | Cleared | 1/10/2023 | BRENNEN OBETO |
| ZI | Cleared | 1/10/2023 | BRENNEN OBETO |
| ZI | Cleared | 1/18/2023 | BRENNEN OBETO |
| Low Impact Development | Cleared | 2/2/2023 | ROGELIO CORTES |
| Low Impact Development | Cleared | 2/2/2023 | ROGELIO CORTES |
| Eng Process Fee Ord 176,300 | Cleared | 2/16/2023 | COLIN LOREDO |
| Miscellaneous | Cleared | 2/22/2023 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 2/22/2023 | COLIN LOREDO |
| Private sewage disp. approval | Cleared | 6/12/2024 | MICHAEL TEMPLE |
| GPI Written Notices | Cleared | 6/19/2024 | GURUNATH NESARAJAH |
| Grading Pre-Inspection | Cleared | 6/19/2024 | GURUNATH NESARAJAH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/24/2024 | Conditional Approval | ROBERT GOLD |
| Underground Mechanical | 8/13/2024 | Partial Approval | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 8/22/2024 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 8/22/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Underground Mechanical | 9/11/2024 | Corrections Issued | KEVIN BERBERYAN |
| Underground Mechanical | 9/13/2024 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 9/23/2024 | Conditional Approval | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 10/2/2024 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Rough | 10/2/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| MERV13>=Rough | 10/2/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 12/11/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 1/7/2025 | Partial Approval | KEVIN BERBERYAN |
| Green Building Rough | 1/7/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| MERV13>=Rough | 1/7/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Deputy Drilled-In Anchors | 4/4/2025 | Conditional Approval | RAUL OLAGI |
| Wood Frame | 6/6/2025 | Partial Approval | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 12/26/2025 | No Access for Inspection | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 1/5/2026 | Corrections Issued | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 1/26/2026 | Approved | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 1/26/2026 | Partial Approval | KEVIN BERBERYAN |
| Insulation | 3/4/2026 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 3/16/2026 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 3/16/2026 | Approved | KEVIN BERBERYAN |
| Shower Pan | 3/16/2026 | Approved | KEVIN BERBERYAN |