17364 W QUESAN PL 91316
Certificate Information: 17364 W QUESAN PL 91316
- Application / Permit
- 22014-20000-05999
- Plan Check / Job No.
- B22VN18091
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED 20'-0" x 20'-0" GARAGE INTO A (N) STUDY ROOM AND HALLWAY AND ADDITION OF (N) ATTACHED 24'-0" x 22'-0" GARAGE TO (E) S.F.D. PER ENGINEERING. SEE COMMENTS
- Permit Issued
- Issued on 3/15/2023
- Issuing Office
- Current Status
- CofO Issued on 10/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/14/2022 | JESSE ARELLANO |
| Corrections Issued | 12/15/2022 | JESSE ARELLANO |
| Applicant returned to address corrections | 3/6/2023 | JESSE ARELLANO |
| Plan Check Approved | 3/15/2023 | ALFRED RAMIREZ |
| Issued | 3/15/2023 | SHANNON HAAS |
| CofO in Progress | 8/4/2023 | VINCENT HANLEY |
| No Progress | 10/4/2023 | VINCENT HANLEY |
| CofO in Progress | 10/4/2023 | VINCENT HANLEY |
| CofO in Progress | 10/6/2023 | SEAN WIRCH |
| Permit Finaled | 10/6/2023 | JOHN JANSON |
| CofO Issued | 10/6/2023 | JOHN JANSON |
| Permit Finaled | 10/6/2023 | JOHN JANSON |
Permit Application Clearance Information
| Low Impact Development | Cleared | 2/10/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 2/13/2023 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/15/2023 | JOSE DUARTE-DIAZ |
| GPI Written Notices | Cleared | 3/6/2023 | JESSE ARELLANO |
| Grading Pre-Inspection | Cleared | 3/6/2023 | JESSE ARELLANO |
| BHO/Hillside ordinance | Cleared | 3/7/2023 | JOSE DUARTE-DIAZ |
| BHO/Hillside ordinance | Cleared | 3/7/2023 | JOSE DUARTE-DIAZ |
| BHO/Hillside ordinance | Cleared | 3/7/2023 | JOSE DUARTE-DIAZ |
| BHO/Hillside ordinance | Cleared | 3/7/2023 | JOSE DUARTE-DIAZ |
| BHO/Hillside ordinance | Cleared | 3/7/2023 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 3/7/2023 | JOSE DUARTE-DIAZ |
| Public Works-Open Permits | Cleared | 3/7/2023 | JOSE DUARTE-DIAZ |
| Public Works-Sewers | Cleared | 3/7/2023 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Jade Construction & Remodeling Inc; Lic. No.: 914387-B | 18257 CALVERT ST TARZANA, CA 91335 |
| Engineer | Sabzehzar,, Habib; Lic. No.: C50442 | 8180 N PRICE AVE FRESNO, CA 93720 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 4/12/2023 | Not Ready for Inspection | VINCENT HANLEY |
| Green Building Rough | 4/12/2023 | Not Ready for Inspection | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 4/21/2023 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 4/21/2023 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 4/21/2023 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2023 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/5/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 5/5/2023 | Approved | VINCENT HANLEY |
| Green Building Rough | 5/5/2023 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 5/5/2023 | Approved | VINCENT HANLEY |
| HVAC-Rough | 5/23/2023 | Approved | SEAN WIRCH |
| Insulation | 5/23/2023 | Approved | SEAN WIRCH |
| Drywall Nailing | 6/2/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 7/19/2023 | Approved | VINCENT HANLEY |
| Final | 7/19/2023 | Not Ready for Inspection | VINCENT HANLEY |
| Green Building Final | 7/19/2023 | Approved | VINCENT HANLEY |
| HVAC-Final | 7/19/2023 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Final | 7/19/2023 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 7/19/2023 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 7/19/2023 | Approved | VINCENT HANLEY |
| Final | 8/3/2023 | Corrections Issued | VINCENT HANLEY |
| Final | 10/4/2023 | Corrections Issued | VINCENT HANLEY |
| Final | 10/10/2023 | OK to Issue CofO | SEAN WIRCH |