12724 W TIARA ST 91607

Certificate Information: 12724 W TIARA ST 91607

Application / Permit
22014-20000-05996
Plan Check / Job No.
B22VN18075
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan Ground floor addition for media room, bathroom, closet, laundry room and patio covers at front and rear to an existing 1-Story, single-family dwelling with attached garage. Work to include new decks, windows, doors, finishes, and skylights.
Permit Issued
Issued on 7/5/2023
Issuing Office
Current Status
CofO Issued on 4/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2022 APPLICANT
Assigned to Plan Check Engineer 12/9/2022 KHUONG TRUONG
Corrections Issued 12/11/2022 KHUONG TRUONG
Applicant returned to address corrections 4/11/2023 SAMUEL GONZALEZ
Applicant returned to address corrections 4/25/2023 SAMUEL GONZALEZ
Plan Check Approved 5/6/2023 SAMUEL GONZALEZ
Issued 7/5/2023 APPLICANT
CofO in Progress 1/21/2025 OGANES TARAKHCHYAN
Permit Finaled 4/1/2025 RUBEN SALAS
CofO Issued 4/1/2025 RUBEN SALAS
Permit Finaled 4/1/2025 RUBEN SALAS

Permit Application Clearance Information

Sewer availability Cleared 2/28/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 3/3/2023 MEGAN GODINEZ
Low Impact Development Cleared 3/22/2023 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 3/24/2023 DAGOVERTO GUERRERO

Contact Information

Architect Glynn,, Frank Christopher; Lic. No.: C19159 233 CALIFORNIA STREET      EL SEGUNDO, CA 90245
Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/18/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 8/22/2023 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 8/25/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 9/1/2023 Partial Approval KIRK SANDERS
Green Building Rough 9/1/2023 Not Ready for Inspection KIRK SANDERS
Underground Mechanical 9/1/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 9/6/2023 Partial Approval CHRISTOPHER ROJAS
Insulation 9/6/2023 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 10/17/2023 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 10/17/2023 Approved KIRK SANDERS
Green Building Rough 10/17/2023 Approved KIRK SANDERS
HVAC-Rough 10/17/2023 Corrections Issued KIRK SANDERS
PLUMBING-Rough 10/17/2023 Approved KIRK SANDERS
Deputy Drilled-In Anchors 10/25/2023 Conditional Approval JUAN VALENZUELA
Deputy Wood Construction 10/25/2023 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 10/27/2023 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 10/27/2023 Approved CHRISTOPHER ROJAS
HVAC-Rough 10/27/2023 Approved CHRISTOPHER ROJAS
Insulation 11/8/2023 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 11/8/2023 Partial Approval KIRK SANDERS
Insulation 11/16/2023 Approved KIRK SANDERS
Drywall Nailing 11/22/2023 Approved JUAN VALENZUELA
Shower Pan 1/11/2024 Approved JOSE AVILA
Wood Frame 2/14/2024 Approved KIRK SANDERS
Drywall Nailing 3/29/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Insulation 3/29/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 3/29/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 9/11/2024 Corrections Issued OGANES TARAKHCHYAN
PLUMBING-Final 9/11/2024 Approved OGANES TARAKHCHYAN
Final 10/10/2024 Corrections Issued OGANES TARAKHCHYAN
Green Building Final 10/10/2024 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 10/10/2024 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 10/10/2024 Approved OGANES TARAKHCHYAN
Final 1/6/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Green Building Final 1/6/2025 Approved GAREN HAYRAPETYAN
Final 1/13/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Final 1/17/2025 OK to Issue CofO OGANES TARAKHCHYAN