17142 W STARE ST 91325
Certificate Information: 17142 W STARE ST 91325
- Application / Permit
- 22014-20000-05964
- Plan Check / Job No.
- B22VN17964
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: ADDITION AND CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELING UNIT PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 4/10/2023
- Issuing Office
- Current Status
- CofO Issued on 9/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2022 | DANIEL YIP |
| Corrections Issued | 12/18/2022 | DANIEL YIP |
| Plan Check Approved | 4/7/2023 | DANIEL YIP |
| Issued | 4/10/2023 | APPLICANT |
| CofO in Progress | 8/21/2023 | JAVIER RAMOS JR |
| Permit Finaled | 9/20/2023 | RUBEN SALAS |
| CofO Issued | 9/20/2023 | RUBEN SALAS |
| Permit Finaled | 9/20/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/20/2022 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2022 | RYAN KIM |
| Sewer availability | Cleared | 12/27/2022 | RYAN KIM |
| Grading Pre-Inspection | Cleared | 1/4/2023 | KIRK LINKLATER |
| Low Impact Development | Cleared | 1/6/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 1/9/2023 | RYAN KIM |
| Construction near power lines | Cleared | 3/27/2023 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 4/7/2023 | DANIEL YIP |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Karapetian,, Arbi; Lic. No.: C79953 | 6854 FOOTHILL BLVD TUJUNGA, CA 91042 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/28/2023 | Corrections Issued | ARAM AVEDISIAN |
| Sewer | 4/28/2023 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 5/2/2023 | Partial Approval | JAVIER RAMOS JR |
| Pre-Inspection | 5/2/2023 | Approved | JAVIER RAMOS JR |
| Sewer | 5/2/2023 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 5/9/2023 | Corrections Issued | JAVIER RAMOS JR |
| Underground Mechanical | 5/9/2023 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 5/31/2023 | Approved | JAVIER RAMOS JR |
| Wood Frame | 5/31/2023 | Corrections Issued | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 6/20/2023 | Partial Approval | JAVIER RAMOS JR |
| Rough-Elec/Plmb/HVAC | 6/20/2023 | Corrections Issued | JAVIER RAMOS JR |
| Underground Mechanical | 6/20/2023 | Approved | JAVIER RAMOS JR |
| Wood Frame | 6/20/2023 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 6/29/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 7/6/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 7/6/2023 | Approved | JAVIER RAMOS JR |
| Gas Test | 7/6/2023 | Partial Approval | JAVIER RAMOS JR |
| Green Building Rough | 7/6/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 7/6/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 7/6/2023 | Approved | JAVIER RAMOS JR |
| Shower Pan | 7/6/2023 | Approved | JAVIER RAMOS JR |
| Wood Frame | 7/6/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 7/12/2023 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 7/12/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 8/16/2023 | Approved | JAVIER RAMOS JR |
| Final | 8/16/2023 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 8/16/2023 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 8/16/2023 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 8/16/2023 | Approved | JAVIER RAMOS JR |