14935 W SYLVAN ST 91411

Certificate Information: 14935 W SYLVAN ST 91411

Application / Permit
22014-20000-05961
Plan Check / Job No.
B22VN17951
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT (E) DETACHED GARAGE WITH (N) 20'-0" x 7'-0" ADDITION INTO A (N) 20'-0" x 25'-0" DETACHED ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33(c) AND (d) AND ADDITION OF 20'-0" x 3'-11" ATTACHED PATIO COVER. ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/28/2023
Issuing Office
Current Status
CofO Issued on 6/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/7/2022 APPLICANT
Assigned to Plan Check Engineer 12/13/2022 ALFRED RAMIREZ
Corrections Issued 12/14/2022 ALFRED RAMIREZ
Plan Check Approved 4/28/2023 JOE VO
Issued 4/28/2023 APPLICANT
CofO in Progress 5/17/2024 RYAN SALAZAR
Permit Finaled 6/14/2024 RUBEN SALAS
Permit Finaled 6/14/2024 RUBEN SALAS
CofO Issued 6/14/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/14/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 12/14/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/21/2022 CARLOS AGUILERA
Sewer availability Cleared 12/21/2022 CARLOS AGUILERA
Construction near power lines Cleared 3/18/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: NA53210       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/22/2023 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 8/25/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 12/6/2023 Not Ready for Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 12/6/2023 Partial Approval RYAN SALAZAR
Green Building Rough 12/6/2023 Not Ready for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 12/15/2023 Not Ready for Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 12/15/2023 Partial Approval RYAN SALAZAR
Green Building Rough 12/15/2023 Not Ready for Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 1/19/2024 Approved RYAN SALAZAR
PLUMBING-Rough 2/6/2024 Approved RYAN SALAZAR
Wood Frame 2/20/2024 Approved RYAN SALAZAR
Insulation 3/1/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 3/5/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 3/5/2024 Partial Approval RYAN SALAZAR
Shower Pan 3/5/2024 Approved RYAN SALAZAR
Drywall Nailing 3/12/2024 Approved RYAN SALAZAR
Green Building Rough 3/12/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 3/12/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 5/6/2024 Approved RYAN SALAZAR
Final 5/6/2024 Corrections Issued RYAN SALAZAR
Green Building Final 5/6/2024 Not Ready for Inspection RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 5/6/2024 SGSOV Approved RYAN SALAZAR
Smoke Detectors 5/6/2024 Approved RYAN SALAZAR
ELECTRICAL-Final 5/13/2024 Corrections Issued JENNIFER RABUCHIN
Final 5/13/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 5/13/2024 Approved JENNIFER RABUCHIN
HVAC-Final 5/13/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 5/13/2024 Approved JENNIFER RABUCHIN
Final 5/16/2024 OK to Issue CofO RYAN SALAZAR
Service/Power Release 5/16/2024 Approved RYAN SALAZAR