10144 N GOTHIC AVE 91343

Certificate Information: 10144 N GOTHIC AVE 91343

Application / Permit
22014-20000-05943
Plan Check / Job No.
B22VN17906
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(E) 18'3" X 20'3" GARAGE AND (N) 16'1" X 10'6" ADDITION TO BE CONVERTED TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
Permit Issued
Issued on 12/21/2022
Issuing Office
Current Status
CofO Issued on 4/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2022 APPLICANT
Assigned to Plan Check Engineer 12/8/2022 JESSE ARELLANO
Corrections Issued 12/10/2022 JESSE ARELLANO
Building Plans Picked Up 12/12/2022 APPLICANT
Applicant returned to address corrections 12/21/2022 SERGIO MUNIZ
Plan Check Approved 12/21/2022 MADISON ODELL
Issued 12/21/2022 APPLICANT
CofO in Progress 4/3/2023 JAVIER RAMOS JR
Permit Finaled 4/18/2023 MICHAEL SMITH
CofO Issued 4/18/2023 MICHAEL SMITH
Permit Finaled 4/18/2023 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 12/16/2022 WALTER RAMIREZ
Address approval Cleared 12/19/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 12/19/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 12/20/2022 MEGAN GODINEZ
Sewer availability Cleared 12/20/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/29/2022 Conditional Approval JAVIER RAMOS JR
Footing/Foundation/Slab 12/30/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 12/30/2022 Partial Approval JAVIER RAMOS JR
Sewer 12/30/2022 Corrections Issued JAVIER RAMOS JR
Underground Mechanical 12/30/2022 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 1/9/2023 Partial Approval JAVIER RAMOS JR
Wood Frame 1/9/2023 Partial Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 1/18/2023 Partial Approval JAVIER RAMOS JR
Rough-Elec/Plmb/HVAC 1/18/2023 Corrections Issued JAVIER RAMOS JR
Underground Mechanical 1/18/2023 Partial Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 1/20/2023 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 1/20/2023 Approved JAVIER RAMOS JR
Green Building Rough 1/20/2023 Approved JAVIER RAMOS JR
Insulation 1/20/2023 Approved JAVIER RAMOS JR
Rough-Elec/Plmb/HVAC 1/20/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 1/25/2023 Approved JAVIER RAMOS JR
Drywall Nailing 1/25/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 1/25/2023 Approved JAVIER RAMOS JR
Shower Pan 1/25/2023 Approved JAVIER RAMOS JR
Underground Mechanical 1/25/2023 Approved JAVIER RAMOS JR
Green Building Final 3/3/2023 Not Ready for Inspection JAVIER RAMOS JR
Pre-Inspection 3/3/2023 Approved JAVIER RAMOS JR
Sewer 3/3/2023 Approved JAVIER RAMOS JR
Underground Mechanical 3/3/2023 Partial Inspection JAVIER RAMOS JR
Final 3/16/2023 Corrections Issued JAVIER RAMOS JR
Green Building Final 3/16/2023 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 3/16/2023 SGSOV Not Ready JAVIER RAMOS JR
Smoke Detectors 3/16/2023 Approved JAVIER RAMOS JR
Final 3/31/2023 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 3/31/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 3/31/2023 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 4/11/2023 Approved JAVIER RAMOS JR