834 N GALLOWAY ST 90272
Certificate Information: 834 N GALLOWAY ST 90272
- Application / Permit
- 22014-20000-05940
- Plan Check / Job No.
- B22VN17888
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL, (N) 26'-11" X 19'-11" ADDITION TO (E) SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 3/9/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2022 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 12/12/2022 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 12/13/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 12/14/2022 | APPLICANT |
| Applicant returned to address corrections | 2/7/2023 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 2/21/2023 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 3/9/2023 | SEWADA ZADOORAN MILAGARDI |
| Issued | 3/9/2023 | APPLICANT |
| Permit Finaled | 5/6/2024 | DANIEL ORRANTE |
| CofO Issued | 5/6/2024 | DANIEL ORRANTE |
| Permit Finaled | 5/6/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/2/2023 | JENSON LEE |
| Sewer availability | Cleared | 2/2/2023 | JENSON LEE |
| Grading Pre-Inspection | Cleared | 2/7/2023 | SEWADA ZADOORAN MILAGARDI |
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2023 | JENSON LEE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Husain,, Shahzain; Lic. No.: C62744 | 1843 MONTGOMERY RD THOUSAND OAKS, CA 91360 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/28/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Grounding or Bonding | 7/28/2023 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/28/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 8/31/2023 | Approved | STEPHANIE SWANSON |
| Wood Frame | 10/3/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2023 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 11/15/2023 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 11/15/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 11/29/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/30/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 11/30/2023 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 11/30/2023 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 11/30/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 11/30/2023 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 12/5/2023 | Approved | EVAN COOPER |
| Drywall Nailing | 12/11/2023 | Approved | ARAM AVEDISIAN |
| Shower Pan | 1/16/2024 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 1/23/2024 | Partial Approval | KENNETH NAGLE |
| Final | 2/29/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 2/29/2024 | SGSOV Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 4/11/2024 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 4/11/2024 | Approved | HERBERT GIRON |
| PLUMBING-Final | 4/11/2024 | Approved | HERBERT GIRON |
| Smoke Detectors | 4/11/2024 | Corrections Issued | HERBERT GIRON |
| Final | 4/16/2024 | Conditional Approval | KENNETH NAGLE |
| Green Building Final | 4/16/2024 | Approved | KENNETH NAGLE |
| Smoke Detectors | 4/16/2024 | Approved | KENNETH NAGLE |