634-636 1/2 E 87TH ST 90002
Certificate Information: 634-636 1/2 E 87TH ST 90002
- Application / Permit
- 22014-20000-05936
- Plan Check / Job No.
- B22VN17854
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan (N) One story Attached ADU per LAMC 12.22 A.33(c) and (e) attached to existing duplex
- Permit Issued
- Issued on 10/12/2023
- Issuing Office
- Current Status
- CofO Issued on 8/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/12/2023 | MARCELA FRANQUEZ |
| Corrections Issued | 1/14/2023 | MARCELA FRANQUEZ |
| Quality Review Completed | 1/23/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 6/30/2023 | MARCELA FRANQUEZ |
| Applicant returned to address corrections | 7/25/2023 | MARCELA FRANQUEZ |
| Plan Check Approved | 8/25/2023 | CHAD DOI |
| Issued | 10/12/2023 | APPLICANT |
| CofO in Progress | 8/6/2025 | JOHN QUINTANILLA |
| Permit Finaled | 8/11/2025 | DEROLD HAUFF |
| CofO Issued | 8/11/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/8/2023 | WALLIE JONG |
| Tenant Habitability Plan | Cleared | 5/8/2023 | ISMAEL HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/9/2023 | WALLIE JONG |
| Low Impact Development | Cleared | 7/24/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 7/25/2023 | WALLIE JONG |
| Sewer availability | Cleared | 7/26/2023 | JEANIE LAM |
Contact Information
| Contractor | Next Generation Builders; Lic. No.: 1069728-B | , |
| Contractor | Polymath Development Group Inc; Lic. No.: 1069728-B | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/15/2023 | Corrections Issued | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 11/30/2023 | Conditional Approval | MICHAEL LEWIS |
| Footing/Foundation/Slab | 11/30/2023 | Conditional Approval | MICHAEL LEWIS |
| Sewer | 1/5/2024 | Approved | MICHAEL LEWIS |
| Gas Test | 2/12/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Underground Mechanical | 2/12/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Underground Mechanical | 3/28/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2024 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 4/10/2024 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2024 | Partial Approval | MICHAEL LEWIS |
| Insulation | 4/15/2024 | Partial Approval | MICHAEL LEWIS |
| ELECTRICAL-Rough | 6/17/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2024 | Corrections Issued | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2024 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 7/3/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| PLUMBING-Rough | 7/16/2024 | Approved | MICHAEL LEWIS |
| Insulation | 9/12/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Interior/Exterior Lathing | 9/12/2024 | Approved | MICHAEL LEWIS |
| Insulation | 9/30/2024 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Rough | 10/1/2024 | Corrections Issued | LUIS CASTRO |
| HVAC-Rough | 10/1/2024 | Corrections Issued | LUIS CASTRO |
| Wood Frame | 10/3/2024 | Corrections Issued | SABAS ALONSO |
| Insulation | 10/4/2024 | Corrections Issued | CRAIG DAVIS |
| Drywall Nailing | 10/8/2024 | Approved | CRAIG DAVIS |
| Green Building Rough | 10/8/2024 | Approved | CRAIG DAVIS |
| HVAC-Rough | 10/29/2024 | Approved | MICHAEL LEWIS |
| Service/Power Release | 5/1/2025 | No Access for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Final | 7/2/2025 | Corrections Issued | JOHN QUINTANILLA |
| HVAC-Final | 7/2/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Final | 7/2/2025 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 7/10/2025 | Approved | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 7/10/2025 | Approved | JOHN QUINTANILLA |
| Final | 7/15/2025 | Corrections Issued | JOHN QUINTANILLA |
| Green Building Final | 7/15/2025 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 7/15/2025 | SGSOV Approved | JOHN QUINTANILLA |
| Smoke Detectors | 7/15/2025 | Approved | JOHN QUINTANILLA |
| Final | 7/18/2025 | Conditional Approval | JOHN QUINTANILLA |
| Final | 8/5/2025 | OK to Issue CofO | JOHN QUINTANILLA |