8822 N ILEX AVE 91352
Certificate Information: 8822 N ILEX AVE 91352
- Application / Permit
- 22014-20000-05931
- Plan Check / Job No.
- B22VN17832
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 12'-0" X 13'-5" ADDITION TO (E) STORAGE/RECROOM AND CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 1/11/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 12/10/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 12/15/2022 | APPLICANT |
| Plan Check Approved | 1/5/2023 | ISIS ARGUETA |
| Issued | 1/11/2023 | APPLICANT |
| CofO in Progress | 4/24/2024 | MATTHEW NELSON |
| Permit Finaled | 5/2/2024 | RUBEN SALAS |
| CofO Issued | 5/2/2024 | RUBEN SALAS |
| Permit Finaled | 5/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/27/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 12/27/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/29/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 12/29/2022 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 12/29/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/5/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 5/5/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 5/15/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2023 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Rough | 5/15/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Rough-Elec/Plmb/HVAC | 5/15/2023 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 5/22/2023 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 5/22/2023 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2023 | Partial Approval | MATTHEW NELSON |
| Green Building Rough | 5/22/2023 | Approved | MATTHEW NELSON |
| MERV13>=Rough | 5/22/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 5/22/2023 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 5/26/2023 | Approved | MATTHEW NELSON |
| Wood Frame | 5/26/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Interior/Exterior Lathing | 6/15/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 6/15/2023 | Approved | MATTHEW NELSON |
| Pre-Inspection | 6/22/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 8/8/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/2/2023 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/23/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 10/23/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Wood Frame | 10/23/2023 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 10/25/2023 | Approved | KEVIN BERBERYAN |
| Insulation | 10/25/2023 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 10/31/2023 | Approved | DAVID ANDERSON |
| Green Building Final | 10/31/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Sewer | 10/31/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 3/29/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 3/29/2024 | Corrections Issued | MATTHEW NELSON |
| MERV13>=Final | 3/29/2024 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 3/29/2024 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 3/29/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 4/15/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 4/15/2024 | Approved | KIRK SANDERS |
| MERV13>=Final | 4/15/2024 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 4/15/2024 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 4/15/2024 | Approved | KIRK SANDERS |
| Final | 4/23/2024 | OK to Issue CofO | MATTHEW NELSON |
| Gas Test | 4/23/2024 | Approved | MATTHEW NELSON |