22157 W DEL VALLE ST 91364
Certificate Information: 22157 W DEL VALLE ST 91364
- Application / Permit
- 22014-20000-05920
- Plan Check / Job No.
- B22VN17802
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF 9'-10" X 9'-6" (93 SQ. FT.) NEW STUDY ROOM TO THE (E) S.F.D PER ENGINEER
- Permit Issued
- Issued on 2/28/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2022 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 12/5/2022 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 1/24/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 2/9/2023 | ANGELICA MARTINEZ |
| Issued | 2/28/2023 | APPLICANT |
| CofO in Progress | 7/14/2023 | PETER FOLLING |
| Permit Finaled | 7/18/2023 | DANIEL ORRANTE |
| CofO Issued | 7/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/22/2022 | ALEXANDER HELFER |
| Eng Process Fee Ord 176,300 | Cleared | 2/9/2023 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 2/9/2023 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 2/9/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Aspire Design And Build; Lic. No.: 1082826-B | 4413 CANOGA DR WOODLAND HILLS, CA 91364 |
| Engineer | Hernandez,, Jose Antonio; Lic. No.: C69472 | 3557 E 58TH ST MAYWOOD, CA 90270 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/16/2023 | Approved | PETER FOLLING |
| Footing/Foundation/Slab | 3/16/2023 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 4/10/2023 | Not Ready for Inspection | PETER FOLLING |
| ELECTRICAL-Rough | 4/10/2023 | Not Ready for Inspection | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2023 | Approved | PETER FOLLING |
| Green Building Rough | 4/10/2023 | Not Ready for Inspection | PETER FOLLING |
| BUILDING-Rough-Frame | 4/18/2023 | Corrections Issued | SEAN HAUPT |
| Green Building Rough | 4/18/2023 | Not Ready for Inspection | SEAN HAUPT |
| Insulation | 4/18/2023 | Not Ready for Inspection | SEAN HAUPT |
| ELECTRICAL-Rough | 4/24/2023 | Approved | PETER FOLLING |
| Insulation | 4/24/2023 | Not Ready for Inspection | PETER FOLLING |
| BUILDING-Rough-Frame | 5/5/2023 | Approved | MORRIS JACKSON |
| Green Building Rough | 5/5/2023 | Approved | MORRIS JACKSON |
| Insulation | 5/5/2023 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 5/5/2023 | Approved | MORRIS JACKSON |
| Drywall Nailing | 5/15/2023 | Approved | PETER FOLLING |
| Interior/Exterior Lathing | 5/15/2023 | Approved | PETER FOLLING |
| Drywall Nailing | 5/17/2023 | Approved | PETER FOLLING |
| Final | 6/21/2023 | Corrections Issued | PETER FOLLING |
| Green Building Final | 6/21/2023 | Approved | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 6/21/2023 | SGSOV Approved | PETER FOLLING |
| Smoke Detectors | 6/21/2023 | Approved | PETER FOLLING |
| Final | 7/13/2023 | OK to Issue CofO | PETER FOLLING |