11330 N BRAINARD AVE 91342

Certificate Information: 11330 N BRAINARD AVE 91342

Application / Permit
22014-20000-05913
Plan Check / Job No.
B22VN17790
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: CONVERSION OF 849 SF (E) SECOND DWELLING UNIT PER PERMIT 14010-20000-03242 TO A DETACHED ADU PER LAMC 12.22 A.33(c) and (d) WITH A 350 SF ADDITION
Permit Issued
Issued on 5/25/2023
Issuing Office
Current Status
CofO Issued on 7/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/3/2022 APPLICANT
Assigned to Plan Check Engineer 12/9/2022 AMY GUEVARRA
Corrections Issued 12/12/2022 AMY GUEVARRA
Applicant returned to address corrections 5/11/2023 AMY GUEVARRA
Plan Check Approved 5/12/2023 AMY GUEVARRA
Issued 5/25/2023 APPLICANT
CofO in Progress 6/24/2024 WILLIAM WREN
Permit Finaled 7/3/2024 RUBEN SALAS
CofO Issued 7/3/2024 RUBEN SALAS
Permit Finaled 7/3/2024 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/3/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 1/9/2023 COLIN LOREDO
Sewer availability Cleared 1/9/2023 COLIN LOREDO
Specific Plan Cleared 1/24/2023 CECILIA CASTILLO
Construction near power lines Cleared 4/15/2023 RIDWAN HARDY
Miscellaneous Cleared 4/18/2023 DALIA MOKAYED
Grading Pre-Inspection Cleared 5/12/2023 AMY GUEVARRA

Contact Information

Contractor Owner-Builder       ,
Engineer Truong,, Phong; Lic. No.: C70784 20439 E CRESTLINE DRIVE      WALNUT, CA 91789

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/25/2023 Approved WILLIAM WREN
PLUMBING-Rough 8/30/2023 Partial Approval WILLIAM WREN
PLUMBING-Rough 9/6/2023 Partial Approval WILLIAM WREN
BUILDING-Rough-Frame 9/14/2023 Partial Approval WILLIAM WREN
Insulation 9/14/2023 Partial Approval WILLIAM WREN
Wood Frame 9/21/2023 Partial Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 10/5/2023 Partial Approval WILLIAM WREN
ELECTRICAL-Rough 10/16/2023 Approved WILLIAM WREN
PLUMBING-Rough 10/16/2023 Approved WILLIAM WREN
Wood Frame 10/16/2023 Corrections Issued WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 11/1/2023 Corrections Issued WILLIAM WREN
Deputy Wood Construction 11/2/2023 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 11/13/2023 No Access for Inspection WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 11/13/2023 Approved WILLIAM WREN
Insulation 11/13/2023 Corrections Issued WILLIAM WREN
Interior/Exterior Lathing 11/13/2023 Partial Approval WILLIAM WREN
MERV13>=Rough 11/13/2023 Approved WILLIAM WREN
Insulation 11/28/2023 Approved WILLIAM WREN
Drywall Nailing 12/6/2023 Approved WILLIAM WREN
BUILDING-Rough-Frame 2/21/2024 Approved WILLIAM WREN
Final 2/21/2024 Corrections Issued WILLIAM WREN
MERV13>=Final 2/21/2024 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 2/21/2024 SGSOV Approved WILLIAM WREN
Smoke Detectors 2/21/2024 Not Ready for Inspection WILLIAM WREN
Final 5/21/2024 Corrections Issued WILLIAM WREN
Smoke Detectors 5/21/2024 Approved WILLIAM WREN
Final 5/31/2024 OK to Issue CofO WILLIAM WREN