11330 N BRAINARD AVE 91342
Certificate Information: 11330 N BRAINARD AVE 91342
- Application / Permit
- 22014-20000-05913
- Plan Check / Job No.
- B22VN17790
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: CONVERSION OF 849 SF (E) SECOND DWELLING UNIT PER PERMIT 14010-20000-03242 TO A DETACHED ADU PER LAMC 12.22 A.33(c) and (d) WITH A 350 SF ADDITION
- Permit Issued
- Issued on 5/25/2023
- Issuing Office
- Current Status
- CofO Issued on 7/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2022 | AMY GUEVARRA |
| Corrections Issued | 12/12/2022 | AMY GUEVARRA |
| Applicant returned to address corrections | 5/11/2023 | AMY GUEVARRA |
| Plan Check Approved | 5/12/2023 | AMY GUEVARRA |
| Issued | 5/25/2023 | APPLICANT |
| CofO in Progress | 6/24/2024 | WILLIAM WREN |
| Permit Finaled | 7/3/2024 | RUBEN SALAS |
| CofO Issued | 7/3/2024 | RUBEN SALAS |
| Permit Finaled | 7/3/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/3/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 1/9/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 1/9/2023 | COLIN LOREDO |
| Specific Plan | Cleared | 1/24/2023 | CECILIA CASTILLO |
| Construction near power lines | Cleared | 4/15/2023 | RIDWAN HARDY |
| Miscellaneous | Cleared | 4/18/2023 | DALIA MOKAYED |
| Grading Pre-Inspection | Cleared | 5/12/2023 | AMY GUEVARRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/25/2023 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 8/30/2023 | Partial Approval | WILLIAM WREN |
| PLUMBING-Rough | 9/6/2023 | Partial Approval | WILLIAM WREN |
| BUILDING-Rough-Frame | 9/14/2023 | Partial Approval | WILLIAM WREN |
| Insulation | 9/14/2023 | Partial Approval | WILLIAM WREN |
| Wood Frame | 9/21/2023 | Partial Approval | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2023 | Partial Approval | WILLIAM WREN |
| ELECTRICAL-Rough | 10/16/2023 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 10/16/2023 | Approved | WILLIAM WREN |
| Wood Frame | 10/16/2023 | Corrections Issued | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2023 | Corrections Issued | WILLIAM WREN |
| Deputy Wood Construction | 11/2/2023 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 11/13/2023 | No Access for Inspection | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2023 | Approved | WILLIAM WREN |
| Insulation | 11/13/2023 | Corrections Issued | WILLIAM WREN |
| Interior/Exterior Lathing | 11/13/2023 | Partial Approval | WILLIAM WREN |
| MERV13>=Rough | 11/13/2023 | Approved | WILLIAM WREN |
| Insulation | 11/28/2023 | Approved | WILLIAM WREN |
| Drywall Nailing | 12/6/2023 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 2/21/2024 | Approved | WILLIAM WREN |
| Final | 2/21/2024 | Corrections Issued | WILLIAM WREN |
| MERV13>=Final | 2/21/2024 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 2/21/2024 | SGSOV Approved | WILLIAM WREN |
| Smoke Detectors | 2/21/2024 | Not Ready for Inspection | WILLIAM WREN |
| Final | 5/21/2024 | Corrections Issued | WILLIAM WREN |
| Smoke Detectors | 5/21/2024 | Approved | WILLIAM WREN |
| Final | 5/31/2024 | OK to Issue CofO | WILLIAM WREN |