22519 W BERDON ST 91367

Certificate Information: 22519 W BERDON ST 91367

Application / Permit
22014-20000-05904
Plan Check / Job No.
B22VN17778
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan Convert portion of existing patio cover to (N) bathroom at rear of existing 1-story single-family dwelling.
Permit Issued
Issued on 3/22/2023
Issuing Office
Current Status
Permit Finaled on 6/6/2023

Permit Application Status History

Submitted 12/6/2022 APPLICANT
Assigned to Plan Check Engineer 12/6/2022 PINANK PATEL
Corrections Issued 12/7/2022 PINANK PATEL
Applicant returned to address corrections 1/5/2023 MINA HABILI
Applicant returned to address corrections 1/9/2023 PINANK PATEL
Plan Check Approved 1/12/2023 MICHAEL LOPEZ
Issued 3/22/2023 APPLICANT
Permit Finaled 6/5/2023 HORACE FULTZ

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/20/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 12/22/2022 COLIN LOREDO
Grading Pre-Inspection Cleared 12/27/2022 ROBERT HUGHES

Contact Information

Contractor J C Construction; Lic. No.: 1064711-B       ,
Engineer Southerland,, Richard Charles; Lic. No.: NA88965       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/24/2023 Conditional Approval KRISTEN CAUSEY
Footing/Foundation/Slab 3/24/2023 Corrections Issued JON MCHUGH
Deputy Drilled-In Anchors 3/28/2023 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 4/3/2023 Partial Approval TROY SANDERS
Footing/Foundation/Slab 4/5/2023 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/13/2023 Partial Approval HORACE FULTZ
PLUMBING-Rough 4/13/2023 Partial Approval HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 4/25/2023 Partial Approval TROY SANDERS
Insulation 4/25/2023 Partial Approval TROY SANDERS
Wood Frame 5/2/2023 Partial Approval HORACE FULTZ
Insulation 5/4/2023 Approved TROY SANDERS
Interior/Exterior Lathing 5/4/2023 Partial Approval TROY SANDERS
Drywall Nailing 5/5/2023 Approved TROY SANDERS
Interior/Exterior Lathing 5/8/2023 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 6/5/2023 Approved HORACE FULTZ
ELECTRICAL-Final 6/5/2023 Approved HORACE FULTZ
Final 6/5/2023 Permit Finaled HORACE FULTZ
HVAC-Final 6/5/2023 Approved HORACE FULTZ
PLUMBING-Final 6/5/2023 Approved HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 6/5/2023 SGSOV Approved HORACE FULTZ
Smoke Detectors 6/5/2023 Approved HORACE FULTZ