6719 N COSTELLO AVE 91405
Certificate Information: 6719 N COSTELLO AVE 91405
- Application / Permit
- 22014-20000-05897
- Plan Check / Job No.
- B22VN17763
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan; Add 476 ft² - new kitchen, bath, powder, relocate laundry , enlarge bedroom. interior remodel per plans . demo portion of dwelling
- Permit Issued
- Issued on 1/9/2023
- Issuing Office
- Current Status
- CofO Issued on 12/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2022 | KHUONG TRUONG |
| Corrections Issued | 12/13/2022 | MINA HABILI |
| Plan Check Approved | 12/28/2022 | KHUONG TRUONG |
| Issued | 1/9/2023 | APPLICANT |
| CofO in Progress | 9/26/2023 | RYAN SALAZAR |
| Permit Finaled | 12/21/2023 | RUBEN SALAS |
| CofO Issued | 12/21/2023 | RUBEN SALAS |
| Permit Finaled | 12/21/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/23/2022 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2022 | RYAN KIM |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Better Together Builders Inc; Lic. No.: 1047689-B | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/15/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 5/17/2023 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 5/17/2023 | Corrections Issued | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2023 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 5/25/2023 | Corrections Issued | RYAN SALAZAR |
| ELECTRICAL-Rough | 5/25/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 5/25/2023 | Approved | RYAN SALAZAR |
| HVAC-Rough | 5/25/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 5/25/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 6/2/2023 | Partial Approval | MATTHEW NELSON |
| Insulation | 6/6/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 6/12/2023 | Partial Approval | WILLIAM WREN |
| Interior/Exterior Lathing | 6/12/2023 | Not Ready for Inspection | WILLIAM WREN |
| Interior/Exterior Lathing | 6/22/2023 | Approved | RYAN SALAZAR |
| Shower Pan | 6/22/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 8/30/2023 | Corrections Issued | RYAN SALAZAR |
| Final | 8/30/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Final | 8/30/2023 | Not Ready for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 8/30/2023 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 8/30/2023 | Corrections Issued | RYAN SALAZAR |
| BUILDING-Rough-Frame | 9/27/2023 | Approved | RYAN SALAZAR |
| Final | 9/27/2023 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 9/27/2023 | Approved | RYAN SALAZAR |
| Smoke Detectors | 9/27/2023 | Approved | RYAN SALAZAR |