13676 W WEIDNER ST 91331
Certificate Information: 13676 W WEIDNER ST 91331
- Application / Permit
- 22014-20000-05885
- Plan Check / Job No.
- B22VN17743
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 32' X 16' IRR. SHAPED ADDITION & REMODEL TO (E) SFD TO ADD 2 BEDROOMS, 2 BATHROOMS, AND A LAUNDRY ROOM. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 12/20/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 12/5/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 12/8/2022 | APPLICANT |
| Issued | 12/20/2022 | APPLICANT |
| CofO in Progress | 9/3/2025 | MICHEL ABAJAN |
| Permit Finaled | 9/9/2025 | RUBEN SALAS |
| CofO Issued | 9/9/2025 | RUBEN SALAS |
| Permit Finaled | 9/9/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/12/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 12/13/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/19/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/29/2023 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 1/4/2024 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 1/4/2024 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 1/4/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 6/27/2024 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 6/27/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 6/27/2024 | Approved | MICHEL ABAJAN |
| Sewer | 6/27/2024 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 7/2/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/3/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 7/3/2024 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 7/3/2024 | Approved | MICHEL ABAJAN |
| Insulation | 7/18/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 7/18/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 10/24/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/18/2025 | Approved | MICHEL ABAJAN |
| Final | 7/18/2025 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 7/18/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 7/18/2025 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 7/18/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/18/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/18/2025 | SGSOV Not Ready | MICHEL ABAJAN |
| Smoke Detectors | 7/18/2025 | Approved | MICHEL ABAJAN |
| Final | 8/18/2025 | Corrections Issued | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 8/18/2025 | SGSOV Approved | MICHEL ABAJAN |
| Final | 9/2/2025 | OK to Issue CofO | MICHEL ABAJAN |