7807-7809 N ARCOLA AVE 91352
Certificate Information: 7807-7809 N ARCOLA AVE 91352
- Application / Permit
- 22014-20000-05849
- Plan Check / Job No.
- B22VN17585
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Junior Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT PORTION OF (E) S.F.D. INTO 29' X 23' 7" JUNIOR ACCESSORY DWELLING UNIT TO COMPLY WITH GCS 65852.2(e)(1)(A) AND 65852.22 AND (N) IRREGULAR SHAPED 32'-5" x 27'-11" ADDITION TO (E) S.F.D. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 3/17/2023
- Issuing Office
- Current Status
- CofO Issued on 1/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2022 | ALFRED RAMIREZ |
| Corrections Issued | 12/6/2022 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 1/25/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 3/16/2023 | GURUNATH NESARAJAH |
| Issued | 3/17/2023 | APPLICANT |
| CofO in Progress | 11/27/2023 | DAVID ANDERSON |
| Permit Finaled | 1/3/2024 | RUBEN SALAS |
| CofO Issued | 1/3/2024 | RUBEN SALAS |
| Permit Finaled | 1/3/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/4/2023 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 1/4/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 1/11/2023 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 1/11/2023 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 1/11/2023 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 1/11/2023 | MEGAN GODINEZ |
| Low Impact Development | Cleared | 3/13/2023 | MELINEH AGHAKHABIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vasquez,, Mario A; Lic. No.: C89006 | 1942 SPANISH BROOM DR PALMDALE, CA 93550 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/5/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 6/6/2023 | Corrections Issued | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 6/12/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Sewer | 6/12/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 6/16/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 7/10/2023 | Corrections Issued | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2023 | Approved | DAVID ANDERSON |
| MERV13>=Rough | 7/10/2023 | Approved | DAVID ANDERSON |
| Wood Frame | 7/10/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Interior/Exterior Lathing | 8/22/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 8/29/2023 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 8/29/2023 | Not Ready for Inspection | DAVID ANDERSON |
| HVAC-Rough | 8/29/2023 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 8/29/2023 | Corrections Issued | DAVID ANDERSON |
| Wood Frame | 8/29/2023 | Not Ready for Inspection | DAVID ANDERSON |
| BUILDING-Rough-Frame | 9/1/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 9/1/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 9/1/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 9/1/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 9/1/2023 | Approved | DAVID ANDERSON |
| Shower Pan | 9/1/2023 | Approved | DAVID ANDERSON |
| Insulation | 9/6/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 9/11/2023 | Approved | DAVID ANDERSON |
| Gas Test | 10/16/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 10/16/2023 | SGSOV Approved | MICHEL ABAJAN |
| Underground Mechanical | 10/16/2023 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Final | 11/2/2023 | Corrections Issued | DAVID MATSON |
| Final | 11/2/2023 | Corrections Issued | DAVID MATSON |
| Footing/Foundation/Slab | 11/2/2023 | Approved | DAVID MATSON |
| HVAC-Final | 11/2/2023 | Approved | DAVID MATSON |
| MERV13>=Final | 11/2/2023 | Approved | DAVID MATSON |
| PLUMBING-Final | 11/2/2023 | Corrections Issued | DAVID MATSON |
| Service/Power Release | 11/2/2023 | Not Ready for Inspection | DAVID MATSON |
| Smoke Detectors | 11/2/2023 | Approved | DAVID MATSON |
| Verify Rec and Parks Fee Memo | 11/2/2023 | Approved | DAVID MATSON |
| ELECTRICAL-Final | 11/8/2023 | Approved | DAVID ANDERSON |
| Final | 11/8/2023 | Not Ready for Inspection | DAVID ANDERSON |
| HVAC-Final | 11/8/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Final | 11/8/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Service/Power Release | 11/8/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 11/15/2023 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Final | 11/15/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Service/Power Release | 11/15/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 11/21/2023 | OK to Issue CofO | DAVID ANDERSON |
| Service/Power Release | 11/21/2023 | Approved | DAVID ANDERSON |