720 E 92ND ST 90002
Certificate Information: 720 E 92ND ST 90002
- Application / Permit
- 22014-20000-05842
- Plan Check / Job No.
- B22VN17554
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: 2-STORY ACCESSORY DWELLING UNIT AND GARAGE ADDITION TO (E) 1-STORY GARAGE PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 6/16/2023
- Issuing Office
- Current Status
- CofO Issued on 1/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/4/2023 | DANIEL YIP |
| Corrections Issued | 1/4/2023 | DANIEL YIP |
| Quality Review Completed | 1/4/2023 | GARO TELMI |
| Applicant returned to address corrections | 5/9/2023 | DANIEL YIP |
| Applicant returned to address corrections | 5/22/2023 | DANIEL YIP |
| Plan Check Approved | 6/15/2023 | DANIEL YIP |
| Issued | 6/16/2023 | APPLICANT |
| CofO in Progress | 1/9/2024 | MICHAEL LEWIS |
| CofO Issued | 1/10/2024 | DEROLD HAUFF |
| Permit Finaled | 1/10/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/27/2023 | RIDWAN HARDY |
| Address approval | Cleared | 3/20/2023 | CHRISTOPHER ROCHA |
| Low Impact Development | Cleared | 4/3/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 4/3/2023 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2023 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 4/18/2023 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Stewart,, Carl; Lic. No.: NA86681 | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/28/2023 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Rough | 7/28/2023 | Partial Inspection | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 8/2/2023 | Partial Approval | MICHAEL LEWIS |
| Footing/Foundation/Slab | 8/2/2023 | Partial Approval | MICHAEL LEWIS |
| Underground Mechanical | 8/2/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 8/10/2023 | Approved | MICHAEL LEWIS |
| Deputy Steel/Welding | 8/15/2023 | Conditional Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2023 | Corrections Issued | MICHAEL LEWIS |
| Structural Steel Frame | 8/23/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2023 | Partial Approval | MICHAEL LEWIS |
| ELECTRICAL-Rough | 9/25/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 9/25/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 9/25/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 10/2/2023 | Corrections Issued | MICHAEL LEWIS |
| Green Building Rough | 10/2/2023 | Approved | MICHAEL LEWIS |
| Insulation | 10/5/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 10/5/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 10/12/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 11/22/2023 | Partial Approval | RONNIE MINDANAO |
| Underground Mechanical | 11/28/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 12/21/2023 | Partial Inspection | MICHAEL LEWIS |
| Final | 12/21/2023 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 12/21/2023 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 12/21/2023 | SGSOV Approved | MICHAEL LEWIS |
| Smoke Detectors | 12/21/2023 | Corrections Issued | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 12/27/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 12/27/2023 | Approved | MICHAEL LEWIS |
| Final | 12/27/2023 | Conditional Approval | MICHAEL LEWIS |
| Service/Power Release | 12/27/2023 | Approved | MICHAEL LEWIS |
| Smoke Detectors | 12/27/2023 | Approved | MICHAEL LEWIS |
| Final | 1/8/2024 | OK to Issue CofO | MICHAEL LEWIS |