720 E 92ND ST 90002

Certificate Information: 720 E 92ND ST 90002

Application / Permit
22014-20000-05842
Plan Check / Job No.
B22VN17554
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: 2-STORY ACCESSORY DWELLING UNIT AND GARAGE ADDITION TO (E) 1-STORY GARAGE PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 6/16/2023
Issuing Office
Current Status
CofO Issued on 1/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/1/2022 APPLICANT
Assigned to Plan Check Engineer 1/4/2023 DANIEL YIP
Corrections Issued 1/4/2023 DANIEL YIP
Quality Review Completed 1/4/2023 GARO TELMI
Applicant returned to address corrections 5/9/2023 DANIEL YIP
Applicant returned to address corrections 5/22/2023 DANIEL YIP
Plan Check Approved 6/15/2023 DANIEL YIP
Issued 6/16/2023 APPLICANT
CofO in Progress 1/9/2024 MICHAEL LEWIS
CofO Issued 1/10/2024 DEROLD HAUFF
Permit Finaled 1/10/2024 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 2/27/2023 RIDWAN HARDY
Address approval Cleared 3/20/2023 CHRISTOPHER ROCHA
Low Impact Development Cleared 4/3/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 4/3/2023 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 4/18/2023 CHRISTOPHER ROCHA
Sewer availability Cleared 4/18/2023 CHRISTOPHER ROCHA

Contact Information

Contractor Owner-Builder       ,
Engineer Stewart,, Carl; Lic. No.: NA86681       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/28/2023 Corrections Issued MICHAEL LEWIS
PLUMBING-Rough 7/28/2023 Partial Inspection MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 8/2/2023 Partial Approval MICHAEL LEWIS
Footing/Foundation/Slab 8/2/2023 Partial Approval MICHAEL LEWIS
Underground Mechanical 8/2/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 8/10/2023 Approved MICHAEL LEWIS
Deputy Steel/Welding 8/15/2023 Conditional Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 8/23/2023 Corrections Issued MICHAEL LEWIS
Structural Steel Frame 8/23/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 8/28/2023 Partial Approval MICHAEL LEWIS
ELECTRICAL-Rough 9/25/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 9/25/2023 Approved MICHAEL LEWIS
HVAC-Rough 9/25/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 9/25/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 10/2/2023 Corrections Issued MICHAEL LEWIS
Green Building Rough 10/2/2023 Approved MICHAEL LEWIS
Insulation 10/5/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 10/5/2023 Approved MICHAEL LEWIS
Drywall Nailing 10/12/2023 Approved MICHAEL LEWIS
Underground Mechanical 11/22/2023 Partial Approval RONNIE MINDANAO
Underground Mechanical 11/28/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 12/21/2023 Partial Inspection MICHAEL LEWIS
Final 12/21/2023 Corrections Issued MICHAEL LEWIS
Green Building Final 12/21/2023 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 12/21/2023 SGSOV Approved MICHAEL LEWIS
Smoke Detectors 12/21/2023 Corrections Issued MICHAEL LEWIS
BUILDING-Rough-Frame 12/27/2023 Approved MICHAEL LEWIS
ELECTRICAL-Final 12/27/2023 Approved MICHAEL LEWIS
Final 12/27/2023 Conditional Approval MICHAEL LEWIS
Service/Power Release 12/27/2023 Approved MICHAEL LEWIS
Smoke Detectors 12/27/2023 Approved MICHAEL LEWIS
Final 1/8/2024 OK to Issue CofO MICHAEL LEWIS