632 E 118TH PL 90059
Certificate Information: 632 E 118TH PL 90059
- Application / Permit
- 22014-20000-05820
- Plan Check / Job No.
- B22VN17480
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 30'-3" X 11'-4" ADDITION TO (E) SFD, ALL WORK PER ENG.
- Permit Issued
- Issued on 10/19/2023
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 8/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2022 | SERGIO MUNIZ |
| Corrections Issued | 12/1/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 12/2/2022 | APPLICANT |
| Plan Check Approved | 4/6/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 4/6/2023 | RICARDO RAMIREZ |
| No Progress | 10/19/2023 | RICARDO RAMIREZ |
| Issued | 10/19/2023 | APPLICANT |
| CofO in Progress | 8/6/2024 | JOSEPH MCGARRY |
| CofO Issued | 8/6/2024 | ANSON MAGLASANG |
| Permit Finaled | 8/6/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/23/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2023 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kator,, Khaled; Lic. No.: C69781 | 19519 TULSA ST NORTHRIDGE, CA 91326 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/14/2023 | Corrections Issued | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 11/20/2023 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 11/20/2023 | Partial Approval | JOHN KLARIN |
| Footing/Foundation/Slab | 11/27/2023 | Corrections Issued | JAMES CHAVEZ |
| Deputy Drilled-In Anchors | 11/29/2023 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 12/1/2023 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 12/21/2023 | Partial Approval | JOHN KLARIN |
| Green Building Rough | 12/21/2023 | Not Ready for Inspection | JOHN KLARIN |
| MERV13>=Rough | 12/21/2023 | Not Ready for Inspection | JOHN KLARIN |
| Deputy Drilled-In Anchors | 12/22/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 1/22/2024 | Corrections Issued | JAMES CHAVEZ |
| ELECTRICAL-Rough | 1/22/2024 | Corrections Issued | JAMES CHAVEZ |
| PLUMBING-Rough | 1/22/2024 | Corrections Issued | JAMES CHAVEZ |
| Wood Frame | 1/22/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2024 | Approved | BEN MOLSTAD |
| Insulation | 3/21/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 4/16/2024 | Approved | BEN MOLSTAD |
| HVAC-Rough | 4/16/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 4/16/2024 | Approved | BEN MOLSTAD |
| Drywall Nailing | 5/14/2024 | Approved | BEN MOLSTAD |
| Green Building Rough | 5/14/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 5/14/2024 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 6/27/2024 | Approved | BEN MOLSTAD |
| Final | 6/27/2024 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 6/27/2024 | Not Ready for Inspection | BEN MOLSTAD |
| MERV13>=Final | 6/27/2024 | Approved | BEN MOLSTAD |
| MERV13>=Rough | 6/27/2024 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 6/27/2024 | SGSOV Approved | BEN MOLSTAD |
| Smoke Detectors | 6/27/2024 | Approved | BEN MOLSTAD |
| Final | 8/1/2024 | OK to Issue CofO | JOSEPH MCGARRY |
| Green Building Final | 8/1/2024 | Approved | JOSEPH MCGARRY |