13056 W DELANO ST 91401
Certificate Information: 13056 W DELANO ST 91401
- Application / Permit
- 22014-20000-05792
- Plan Check / Job No.
- B22VN17412
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* GROUND FLOOR ADDITION (ZC: 288 SF) TO (E) 1-STORY SFD WITH (E) ATTACHED GARAGE AND INTERIOR REMODEL.
- Permit Issued
- Issued on 2/26/2023
- Issuing Office
- Current Status
- CofO Issued on 3/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/29/2022 | VIVIAN LAO |
| Corrections Issued | 11/30/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 2/17/2023 | DANIEL YIP |
| Plan Check Approved | 2/24/2023 | DANIEL YIP |
| Issued | 2/26/2023 | APPLICANT |
| CofO in Progress | 10/2/2023 | KIRK SANDERS |
| Permit Finaled | 3/20/2024 | RUBEN SALAS |
| Permit Finaled | 3/20/2024 | RUBEN SALAS |
| CofO Issued | 3/20/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/12/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 1/12/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2023 | DAGOVERTO GUERRERO |
Contact Information
| Architect | Di, Zitti, Fernando; Lic. No.: NA24587 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/10/2023 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 4/18/2023 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Rough | 6/14/2023 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 7/7/2023 | Approved | KIRK SANDERS |
| Green Building Rough | 7/7/2023 | Approved | KIRK SANDERS |
| HVAC-Rough | 7/7/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 7/7/2023 | Approved | KIRK SANDERS |
| Insulation | 7/18/2023 | Approved | THOMAS FINNILA |
| Drywall Nailing | 8/8/2023 | Approved | KIRK SANDERS |
| Final | 9/21/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 9/21/2023 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 9/21/2023 | SGSOV Not Ready | KIRK SANDERS |
| Smoke Detectors | 9/21/2023 | Corrections Issued | KIRK SANDERS |
| Final | 9/28/2023 | OK to Issue CofO | KIRK SANDERS |
| HVAC-Final | 9/28/2023 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 9/28/2023 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 9/28/2023 | Approved | KIRK SANDERS |