13056 W DELANO ST 91401

Certificate Information: 13056 W DELANO ST 91401

Application / Permit
22014-20000-05792
Plan Check / Job No.
B22VN17412
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* GROUND FLOOR ADDITION (ZC: 288 SF) TO (E) 1-STORY SFD WITH (E) ATTACHED GARAGE AND INTERIOR REMODEL.
Permit Issued
Issued on 2/26/2023
Issuing Office
Current Status
CofO Issued on 3/20/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/29/2022 APPLICANT
Assigned to Plan Check Engineer 11/29/2022 VIVIAN LAO
Corrections Issued 11/30/2022 VIVIAN LAO
Applicant returned to address corrections 2/17/2023 DANIEL YIP
Plan Check Approved 2/24/2023 DANIEL YIP
Issued 2/26/2023 APPLICANT
CofO in Progress 10/2/2023 KIRK SANDERS
Permit Finaled 3/20/2024 RUBEN SALAS
Permit Finaled 3/20/2024 RUBEN SALAS
CofO Issued 3/20/2024 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/12/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 1/12/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 2/10/2023 DAGOVERTO GUERRERO

Contact Information

Architect Di, Zitti, Fernando; Lic. No.: NA24587       ,
Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/10/2023 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 4/18/2023 Approved JUAN VALENZUELA
ELECTRICAL-Rough 6/14/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 6/14/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 7/7/2023 Approved KIRK SANDERS
Green Building Rough 7/7/2023 Approved KIRK SANDERS
HVAC-Rough 7/7/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 7/7/2023 Approved KIRK SANDERS
Insulation 7/18/2023 Approved THOMAS FINNILA
Drywall Nailing 8/8/2023 Approved KIRK SANDERS
Final 9/21/2023 Corrections Issued KIRK SANDERS
Green Building Final 9/21/2023 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 9/21/2023 SGSOV Not Ready KIRK SANDERS
Smoke Detectors 9/21/2023 Corrections Issued KIRK SANDERS
Final 9/28/2023 OK to Issue CofO KIRK SANDERS
HVAC-Final 9/28/2023 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 9/28/2023 SGSOV Approved KIRK SANDERS
Smoke Detectors 9/28/2023 Approved KIRK SANDERS