6303 N ELMER AVE 91606
Certificate Information: 6303 N ELMER AVE 91606
- Application / Permit
- 22014-20000-05768
- Plan Check / Job No.
- B22VN17372
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL, (N) 16-1" X 21'-1" ADDITION TO REAR, 20'-4"X 9'-5" AND 5'-7" X 15'-8" ADDITION TO FRONT OF (E) ONE STORY SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT
- Permit Issued
- Issued on 3/21/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2022 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 12/19/2022 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 12/23/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 12/28/2022 | APPLICANT |
| Plan Check Approved | 3/15/2023 | SEWADA ZADOORAN MILAGARDI |
| Issued | 3/21/2023 | APPLICANT |
| CofO in Progress | 1/24/2024 | CRAIG DAVIS |
| Permit Finaled | 3/29/2024 | DANIEL ORRANTE |
| CofO Issued | 3/29/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/29/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 1/11/2023 | MEGAN GODINEZ |
| Low Impact Development | Cleared | 3/8/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 3/9/2023 | JOHN LIN |
Contact Information
| Architect | Libit,, Bryan Andrew; Lic. No.: C33010 | 2421 SILVER RIDGE AVENUE LOS ANGELES, CA 90039 |
| Contractor | Morshedi Ahmad; Lic. No.: 932714-B | 2401 SOUTH SANTA FE AVENUE #103 LOS ANGELES, CA 90058 |
| Engineer | Garcia,, Francisco Javier; Lic. No.: C76510 | 2705 S FREMONT AVE APT D ALHAMBRA, CA 91803 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/7/2023 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 4/12/2023 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 4/21/2023 | Partial Approval | JOHN HAYES |
| Deputy Drilled-In Anchors | 4/25/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 4/25/2023 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 5/12/2023 | Partial Approval | JOHN HAYES |
| Wood Frame | 5/12/2023 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2023 | Partial Approval | JACK KARGODORIAN |
| Wood Frame | 6/22/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Rough | 7/27/2023 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 7/27/2023 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2023 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 8/3/2023 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 8/15/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 8/15/2023 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 8/22/2023 | Approved | JOHN HAYES |
| Green Building Rough | 8/22/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 8/22/2023 | Partial Approval | JOHN HAYES |
| Shower Pan | 8/22/2023 | Corrections Issued | JOHN HAYES |
| Insulation | 8/25/2023 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 8/25/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 8/31/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/31/2023 | Approved | JENNIFER RABUCHIN |
| Final | 12/4/2023 | Corrections Issued | JOHN HAYES |
| Green Building Final | 12/4/2023 | Approved | JOHN HAYES |
| PLUMBING-Final | 12/4/2023 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 12/4/2023 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 12/4/2023 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 12/26/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 12/26/2023 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 12/26/2023 | Approved | JENNIFER RABUCHIN |
| Final | 1/18/2024 | Corrections Issued | CRAIG DAVIS |
| Final | 1/23/2024 | OK to Issue CofO | CRAIG DAVIS |