12318 W RYE ST 91604
Certificate Information: 12318 W RYE ST 91604
- Application / Permit
- 22014-20000-05765
- Plan Check / Job No.
- B22VN17362
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 13'-6" x 4'-0" AND 8'-0" x 13'-6" ADDITION TO (E) DETACHED GARAGE AND CONVERT (E) GARAGE INTO A (N) IRREGULAR SHAPED DETACHED 30'-0" x 24'-0" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 7/31/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/28/2022 | JESSE ARELLANO |
| Corrections Issued | 11/28/2022 | JESSE ARELLANO |
| Building Plans Picked Up | 11/30/2022 | APPLICANT |
| Plan Check Approved | 7/28/2023 | ALFRED RAMIREZ |
| Issued | 7/31/2023 | APPLICANT |
| CofO in Progress | 6/26/2024 | CHRISTOPHE COCHRAN |
| Permit Finaled | 8/7/2024 | RUBEN SALAS |
| CofO Issued | 8/7/2024 | RUBEN SALAS |
| Permit Finaled | 8/7/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/22/2023 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 3/22/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 3/24/2023 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 5/26/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/6/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gonzalez,, Jorge Alberto; Lic. No.: C88762 | 859 BUTTE ST MC FARLAND, CA 93250 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/7/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Underground Mechanical | 8/7/2023 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 8/14/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Deputy Drilled-In Anchors | 8/23/2023 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 8/23/2023 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 10/5/2023 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 10/5/2023 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 10/5/2023 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 11/3/2023 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 11/3/2023 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 11/7/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Shower Pan | 11/7/2023 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 11/13/2023 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 11/17/2023 | Approved | CHRISTOPHER ROJAS |
| Gas Test | 3/14/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 3/14/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 4/18/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| HVAC-Final | 4/18/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| MERV13>=Final | 4/18/2024 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 4/18/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 5/28/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 5/28/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 5/28/2024 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 5/28/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 5/28/2024 | Approved | CHRISTOPHE COCHRAN |
| Final | 6/26/2024 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Green Building Final | 6/26/2024 | Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 6/26/2024 | Approved | CHRISTOPHE COCHRAN |
| Pre-Inspection | 7/25/2024 | Corrections Issued | CHRISTOPHE COCHRAN |