6235 N AGNES AVE 91606

Certificate Information: 6235 N AGNES AVE 91606

Application / Permit
22014-20000-05749
Plan Check / Job No.
B22VN17320
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EX FAMILY RM INTO BEDRM & CLOSET W/ 7'1"X7'11" BATHRM ADDN. REFREAME ROOF OVER NEW BEDRM PER PLAN. REMODEL EX LAUNDRY RM. ALL WORK PER ENGR DESIGN.
Permit Issued
Issued on 12/9/2022
Issuing Office
Valley
Current Status
CofO Issued on 12/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2022 APPLICANT
Assigned to Plan Check Engineer 11/25/2022 HAYATO TSUCHIYA
Corrections Issued 11/25/2022 HAYATO TSUCHIYA
Building Plans Picked Up 11/28/2022 APPLICANT
Plan Check Approved 12/9/2022 MOHAMMAD ESMAILI
Issued 12/9/2022 APPLICANT
CofO in Progress 9/27/2023 JOHN HAYES
Permit Finaled 12/6/2023 RUBEN SALAS
CofO Issued 12/6/2023 RUBEN SALAS
Permit Finaled 12/6/2023 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/7/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 12/8/2022 CARLOS AGUILERA
Low Impact Development Cleared 12/8/2022 MARTIN FRAGOSO
Sewer availability Cleared 12/8/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/24/2023 Approved THOMAS FINNILA
PLUMBING-Rough 5/4/2023 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 5/8/2023 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 5/18/2023 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/18/2023 Approved JENNIFER RABUCHIN
Gas Test 5/18/2023 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 5/18/2023 Approved JENNIFER RABUCHIN
PLUMBING-Rough 5/18/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 5/24/2023 Partial Approval JOHN HAYES
Wood Frame 5/24/2023 Approved JOHN HAYES
Insulation 6/1/2023 Approved JOHN HAYES
Drywall Nailing 6/9/2023 Approved JOHN HAYES
Green Building Rough 6/9/2023 Approved JOHN HAYES
Shower Pan 6/9/2023 Not Ready for Inspection JOHN HAYES
Shower Pan 6/16/2023 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 9/1/2023 Approved JOHN HAYES
Final 9/1/2023 Corrections Issued JOHN HAYES
Green Building Final 9/1/2023 Approved JOHN HAYES
MERV13>=Final 9/1/2023 Approved JOHN HAYES
MERV13>=Rough 9/1/2023 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 9/1/2023 SGSOV Approved JOHN HAYES
Smoke Detectors 9/1/2023 Approved JOHN HAYES
Final 9/21/2023 Corrections Issued JOHN HAYES
Final 9/27/2023 OK to Issue CofO JOHN HAYES