11930 N CAPISTRANO LANE 91326

Certificate Information: 11930 N CAPISTRANO LANE 91326

Application / Permit
22014-20000-05736
Plan Check / Job No.
B22VN17273
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: (N) ATTACHED DECK TO (E) SINGLE FAMILY DWELLING
Permit Issued
Issued on 5/2/2023
Issuing Office
Current Status
CofO Issued on 3/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2022 APPLICANT
Assigned to Plan Check Engineer 11/28/2022 DANIEL YIP
Corrections Issued 11/29/2022 DANIEL YIP
Applicant returned to address corrections 3/10/2023 DANIEL YIP
Plan Check Approved 5/2/2023 DANIEL YIP
Issued 5/2/2023 APPLICANT
CofO in Progress 3/6/2024 JEFFREY PARD
Permit Finaled 3/15/2024 JOHN JANSON
CofO Issued 3/15/2024 JOHN JANSON
Permit Finaled 3/15/2024 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/9/2023 ALEXANDER HELFER
Roof/Waste drainage to street Cleared 3/3/2023 MATTHEW MAHLEBASHIAN
Eng Process Fee Ord 176,300 Cleared 3/8/2023 MATTHEW MAHLEBASHIAN

Contact Information

Contractor Adar Builders Inc; Lic. No.: 1051859-B       ,
Engineer Farish,, William Crawford; Lic. No.: C30123 19432 CASTLEWOOD CR      HUNTINGTON BEACH, CA 92648
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/25/2023 Approved SEAN HAUPT
Footing/Foundation/Slab 5/25/2023 Approved SEAN HAUPT
METHANE-Barrier 5/25/2023 Approved SEAN HAUPT
METHANE-Rough 5/25/2023 Approved SEAN HAUPT
METHANE-Subgrade 5/25/2023 Approved SEAN HAUPT
Special/Order Compliance 5/25/2023 Corrections Issued SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 5/30/2023 Partial Approval STEVEN BACK
ELECTRICAL-Rough 6/7/2023 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 6/7/2023 Approved SEAN WIRCH
Wood Frame 6/7/2023 Partial Approval SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 6/8/2023 Not Ready for Inspection JEFFREY PARD
BUILDING-Rough-Frame 6/15/2023 Corrections Issued STEVEN BACK
Green Building Rough 6/15/2023 Not Ready for Inspection STEVEN BACK
Insulation 6/15/2023 Approved STEVEN BACK
Interior/Exterior Lathing 6/15/2023 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 6/23/2023 Corrections Issued STEVEN BACK
Drywall Nailing 6/23/2023 Partial Approval STEVEN BACK
Interior/Exterior Lathing 6/23/2023 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 6/28/2023 Not Ready for Inspection STEVEN BACK
Green Building Rough 6/28/2023 Approved STEVEN BACK
Interior/Exterior Lathing 6/28/2023 Approved STEVEN BACK
BUILDING-Rough-Frame 10/13/2023 Corrections Issued STEVEN BACK
Drywall Nailing 10/13/2023 Not Ready for Inspection STEVEN BACK
Final 10/13/2023 Corrections Issued STEVEN BACK
Green Building Final 10/13/2023 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 10/13/2023 SGSOV Gas Company STEVEN BACK
Smoke Detectors 10/13/2023 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 1/29/2024 Approved JEFFREY PARD
Drywall Nailing 1/29/2024 Approved JEFFREY PARD
Final 1/29/2024 OK to Issue CofO JEFFREY PARD
Smoke Detectors 1/29/2024 Approved JEFFREY PARD