2244 S MANNING AVE 90064

Certificate Information: 2244 S MANNING AVE 90064

Application / Permit
22014-20000-05735
Plan Check / Job No.
B22VN17268
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2ND STORY ADDITION TO (E) 2-STORY SFD
Permit Issued
Issued on 6/7/2023
Issuing Office
West Los Angeles
Current Status
Issued on 6/7/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/21/2022 APPLICANT
Assigned to Plan Check Engineer 12/1/2022 SELLA BENYAMIN
Corrections Issued 12/6/2022 SELLA BENYAMIN
Quality Review Completed 12/8/2022 STEVEN KIM
Building Plans Picked Up 12/13/2022 APPLICANT
Plan Check Approved 3/10/2023 SELLA BENYAMIN
Issued 6/7/2023 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/27/2023 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 2/7/2023 JENSON LEE

Contact Information

Architect Samson,, Charles Andrew H; Lic. No.: C22979 6119 MARY ELLEN AVENUE      VAN NUYS, CA 91401
Contractor Kempler & Company Incorporated; Lic. No.: 562533-B 14731 SUTTON STREET      SHERMAN OAKS, CA 91403
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 12/18/2024 Partial Approval STEPHANIE SWANSON
HVAC-Rough 12/18/2024 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 12/18/2024 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 12/20/2024 Partial Approval STEPHANIE SWANSON
Green Building Rough 12/20/2024 Not Ready for Inspection STEPHANIE SWANSON
Drywall Nailing 12/24/2024 Partial Approval JESUS RODRIGUEZ
Deputy Drilled-In Anchors 5/1/2025 Conditional Approval DANIEL VERA
Excavation/Setback/Form/Re-Bar 5/15/2025 Corrections Issued DANIEL VERA
Deputy Drilled-In Anchors 5/27/2025 Approved DANIEL VERA
Excavation/Setback/Form/Re-Bar 5/27/2025 Approved DANIEL VERA
Deputy Wood Construction 6/12/2025 Approved DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 6/12/2025 Partial Approval DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 6/13/2025 Partial Approval DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 6/25/2025 Partial Approval DANIEL VERA
Pre-Inspection 6/25/2025 Approved DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 6/30/2025 Partial Approval DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 7/1/2025 Partial Approval DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 7/10/2025 Partial Approval DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 7/14/2025 Corrections Issued DANIEL VERA
PLUMBING-Rough 7/15/2025 Approved DANIEL VERA
BUILDING-Rough-Frame 7/17/2025 Partial Approval DANIEL VERA
ELECTRICAL-Rough 7/17/2025 Approved DANIEL VERA
HVAC-Rough 7/17/2025 Approved DANIEL VERA
Drywall Nailing 7/23/2025 Partial Approval DANIEL VERA
Shower Pan 7/23/2025 Not Ready for Inspection DANIEL VERA
Shower Pan 7/25/2025 Approved DANIEL VERA
Interior/Exterior Lathing 8/7/2025 Approved SEAN HAUPT
Insulation 8/11/2025 Partial Approval DANIEL VERA
Interior/Exterior Lathing 8/11/2025 Partial Approval DANIEL VERA
BUILDING-Rough-Frame 8/13/2025 Approved DANIEL VERA
Green Building Rough 8/13/2025 Approved DANIEL VERA
Insulation 8/14/2025 Approved DANIEL VERA
Drywall Nailing 8/18/2025 Approved DANIEL VERA