8126 N ALCOVE AVE 91605
Certificate Information: 8126 N ALCOVE AVE 91605
- Application / Permit
- 22014-20000-05712
- Plan Check / Job No.
- B22VN17203
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: ADDITION TO REAR OF (E) SINGLE FAMILY RESIDENCE AND INTERIOR REMODEL TO KITCHEN, DINING ROOM AND BEDROOM. ALL WORK PER ENGINEERING. NFPA-13D FIRE SPRINKLER THRU-OUT REQUIRED.
- Permit Issued
- Issued on 4/13/2023
- Issuing Office
- Current Status
- CofO Issued on 2/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2022 | OMAR GARNICA |
| Corrections Issued | 11/23/2022 | OMAR GARNICA |
| Applicant returned to address corrections | 1/11/2023 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 2/25/2023 | DANIEL SANJUAN |
| Plan Check Approved | 3/16/2023 | PINANK PATEL |
| Issued | 4/13/2023 | APPLICANT |
| CofO in Progress | 1/21/2025 | VINCENT HANLEY |
| Permit Finaled | 2/6/2025 | RUBEN SALAS |
| CofO Issued | 2/6/2025 | RUBEN SALAS |
| Permit Finaled | 2/6/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 1/6/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 1/9/2023 | COLIN LOREDO |
Contact Information
| Contractor | Aaa Green Builders; Lic. No.: 1066420-B | , |
| Contractor | Montana Marketing & Sales Inc; Lic. No.: 1066420-B | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/29/2023 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 7/24/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 8/10/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Footing/Foundation/Slab | 8/16/2023 | Corrections Issued | GREGG CUMMINGS |
| Deputy Drilled-In Anchors | 8/23/2023 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 9/28/2023 | Approved | GREGG CUMMINGS |
| Special/Order Compliance | 9/28/2023 | Corrections Issued | GREGG CUMMINGS |
| Wood Frame | 10/23/2023 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/26/2023 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2023 | Partial Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2024 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2024 | Partial Approval | GREGG CUMMINGS |
| Deputy Wood Construction | 1/31/2024 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 2/2/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 2/2/2024 | Approved | GREGG CUMMINGS |
| Green Building Rough | 2/2/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 2/2/2024 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2024 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 4/10/2024 | Corrections Issued | GREGG CUMMINGS |
| Wood Frame | 4/12/2024 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 4/15/2024 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 4/17/2024 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 4/22/2024 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 4/22/2024 | Approved | GREGG CUMMINGS |
| Wood Frame | 4/22/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Deputy Wood Construction | 5/6/2024 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 5/8/2024 | Approved | GREGG CUMMINGS |
| Insulation | 5/8/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 5/8/2024 | Corrections Issued | GREGG CUMMINGS |
| Drywall Nailing | 5/20/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 5/20/2024 | Partial Approval | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 7/15/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Final | 8/7/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 8/7/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 8/7/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 8/7/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 8/20/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 8/20/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 8/20/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 8/20/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 1/6/2025 | No Access for Inspection | VINCENT HANLEY |
| Green Building Final | 1/6/2025 | No Access for Inspection | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 1/6/2025 | SGSOV Not Ready | VINCENT HANLEY |
| Smoke Detectors | 1/6/2025 | No Access for Inspection | VINCENT HANLEY |
| Final | 1/10/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 1/10/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 1/10/2025 | SGSOV Not Ready | VINCENT HANLEY |
| Smoke Detectors | 1/10/2025 | Corrections Issued | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 1/21/2025 | Approved | VINCENT HANLEY |
| Final | 1/21/2025 | OK to Issue CofO | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 1/21/2025 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 1/21/2025 | Approved | VINCENT HANLEY |