11259 W PEACH GROVE ST 91601

Certificate Information: 11259 W PEACH GROVE ST 91601

Application / Permit
22014-20000-05710
Plan Check / Job No.
B22VN17199
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE EXISTING DETACHED 2-CAR GARAGE EXCEPT FOR REAR WALL AND BUILD NEW 2-STORY (34'-10"x27'-2"), 1200 SQFT 2-STORY ACCESSORY DWELLING UNIT W/ROOFTOP DECK ABOVE PER LAMC 12.22 A.33(c)(d)
Permit Issued
Issued on 4/22/2025
Issuing Office
Current Status
Issued on 4/22/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/21/2022 APPLICANT
Assigned to Plan Check Engineer 12/15/2022 PETER MOSESIAN
Corrections Issued 12/23/2022 PETER MOSESIAN
Quality Review Completed 12/30/2022 OMID HEDAYAT
Applicant returned to address corrections 8/8/2023 PETER MOSESIAN
Plan Check Approved 1/11/2024 PETER MOSESIAN
Plan Check Approved 3/10/2025 INTERNET PERMIT
Plan Check Approved 3/10/2025 SEAN SHAHMIRI
Issued 4/22/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/6/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 1/10/2023 ROMAN GUTIERREZ
Sewer availability Cleared 1/10/2023 ROMAN GUTIERREZ
Low Impact Development Cleared 12/4/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 12/5/2023 NIKKI ZULUETA
Address approval Cleared 12/6/2023 NIKKI ZULUETA

Contact Information

Architect Stockton,, Richard Kenneth; Lic. No.: NA35492       ,
Contractor Owner-Builder       ,
Engineer Zolfaghari,, Saeed; Lic. No.: C86761 6201 BEE AVE      AGOURA HILLS, CA 91301

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/2/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 7/3/2025 Partial Approval NICHOLAS TROWBRIDGE
Pre-Inspection 7/3/2025 Partial Approval NICHOLAS TROWBRIDGE
Deputy Drilled-In Anchors 7/8/2025 Approved JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 7/8/2025 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 7/8/2025 Approved JAVIER RAMOS JR
Deputy Wood Construction 8/7/2025 Conditional Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 8/11/2025 Partial Approval JAVIER RAMOS JR
Deputy Wood Construction 9/8/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 9/10/2025 Corrections Issued JAVIER RAMOS JR
Special/Order Compliance 9/10/2025 Corrections Issued JAVIER RAMOS JR
Wood Frame 9/10/2025 Partial Inspection JAVIER RAMOS JR
Wood Frame 11/17/2025 Corrections Issued NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 6/12/2026 Approved DAVID ANDERSON
Insulation 6/23/2026 Approved JAVIER RAMOS JR
Pre-Inspection 6/23/2026 Partial Approval JAVIER RAMOS JR
Drywall Nailing 7/21/2026 Conditional Approval JAVIER RAMOS JR
Interior/Exterior Lathing 7/21/2026 Approved JAVIER RAMOS JR