12115 N GERALD AVE 91344

Certificate Information: 12115 N GERALD AVE 91344

Application / Permit
22014-20000-05696
Plan Check / Job No.
B22VN17185
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
Permit Issued
Issued on 1/29/2023
Issuing Office
Current Status
CofO Issued on 7/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2022 APPLICANT
Assigned to Plan Check Engineer 11/23/2022 DANIEL YIP
Corrections Issued 11/27/2022 DANIEL YIP
Plan Check Approved 1/21/2023 KHUONG TRUONG
Issued 1/29/2023 APPLICANT
CofO in Progress 7/7/2025 CHRISTOPHER ROJAS
Permit Finaled 7/22/2025 RUBEN SALAS
Permit Finaled 7/22/2025 RUBEN SALAS
CofO Issued 7/22/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/29/2022 COLIN LOREDO
Sewer availability Cleared 11/29/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 12/14/2022 COLIN LOREDO
Grading Pre-Inspection Cleared 1/19/2023 DANIEL YIP

Contact Information

Contractor Berardinelli Custom Builders Inc; Lic. No.: 884217-B       ,
Contractor Berardinelli Custom Builders; Lic. No.: 884217-B       ,
Engineer Terrio,, Greyson Franklin; Lic. No.: C87383 22647 VENTURA BLVD 362      WOODLAND HILLS, CA 91364
Engineer Terrio,, Greyson Franklin; Lic. No.: NA87383       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/7/2023 Approved JAVIER RAMOS JR
Deputy Reinf. Concrete 3/9/2023 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 3/28/2023 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 3/28/2023 Approved JAVIER RAMOS JR
Green Building Rough 3/28/2023 Not Ready for Inspection JAVIER RAMOS JR
Deputy Wood Construction 3/29/2023 Conditional Approval MICHAEL SMITH
BUILDING-Rough-Frame 4/6/2023 Approved JAVIER RAMOS JR
Drywall Nailing 4/6/2023 Approved JAVIER RAMOS JR
Green Building Rough 4/6/2023 Approved JAVIER RAMOS JR
HVAC-Rough 4/6/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 4/6/2023 Approved JAVIER RAMOS JR
Deputy Drilled-In Anchors 9/13/2023 Conditional Approval ROBERT GOLD
PLUMBING-Rough 9/14/2023 Partial Approval MICHEL ABAJAN
Pre-Inspection 9/14/2023 Partial Inspection MICHEL ABAJAN
Footing/Foundation/Slab 9/19/2023 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Approved JAVIER RAMOS JR
Insulation 10/30/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 10/30/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Final 1/18/2024 Approved JAVIER RAMOS JR
Final 1/18/2024 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 1/18/2024 Approved JAVIER RAMOS JR
Green Building Final 1/18/2024 Approved JAVIER RAMOS JR
HVAC-Final 1/18/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 1/18/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 1/18/2024 SGSOV Not Required JAVIER RAMOS JR
Smoke Detectors 1/18/2024 Approved JAVIER RAMOS JR
Final 6/5/2025 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 6/5/2025 Approved CHRISTOPHER ROJAS
Final 7/3/2025 OK to Issue CofO CHRISTOPHER ROJAS
PLUMBING-Final 7/3/2025 Approved CHRISTOPHER ROJAS