20210 W TUBA ST 91311
Certificate Information: 20210 W TUBA ST 91311
- Application / Permit
- 22014-20000-05695
- Plan Check / Job No.
- B22VN17183
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 16'-0" X 13'-7" TO AN (E) S.F.D. AND INTERIOR REMODEL. ALL WORK DONE PER ENGINEER.
- Permit Issued
- Issued on 1/3/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2022 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 11/24/2022 | MIROOSH KHACHATOORIAN |
| Building Plans Picked Up | 11/30/2022 | APPLICANT |
| Plan Check Approved | 12/30/2022 | LUISANGEL VALENZUELA |
| Issued | 1/3/2023 | APPLICANT |
| CofO in Progress | 3/26/2024 | DAVID SCANTLIN |
| Permit Finaled | 4/4/2024 | JOHN JANSON |
| CofO Issued | 4/4/2024 | JOHN JANSON |
| Permit Finaled | 4/4/2024 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/29/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/30/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 11/30/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 11/30/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 11/30/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 11/30/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/24/2023 | Partial Approval | DAVID SCANTLIN |
| Special/Order Compliance | 3/24/2023 | Partial Inspection | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 3/31/2023 | Approved | DAVID SCANTLIN |
| Pre-Inspection | 3/31/2023 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 5/18/2023 | Partial Approval | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 6/8/2023 | Approved | DAVID SCANTLIN |
| Green Building Rough | 6/8/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Rough-Elec/Plmb/HVAC | 6/8/2023 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 7/3/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 7/3/2023 | Approved | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 8/10/2023 | Partial Inspection | JOHN KIDWELL |
| Rough-Elec/Plmb/HVAC | 8/14/2023 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 9/13/2023 | Approved | JOHN KIDWELL |
| Green Building Rough | 9/13/2023 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 9/13/2023 | Partial Approval | JOHN KIDWELL |
| Shower Pan | 9/13/2023 | Approved | JOHN KIDWELL |
| Insulation | 9/20/2023 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 9/20/2023 | Not Ready for Inspection | JOHN KIDWELL |
| Drywall Nailing | 9/29/2023 | Partial Approval | JOHN KIDWELL |
| Interior/Exterior Lathing | 9/29/2023 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 10/2/2023 | Approved | DAVID SCANTLIN |
| Final | 3/12/2024 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 3/12/2024 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 3/12/2024 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 3/12/2024 | Approved | DAVID SCANTLIN |
| Final | 3/20/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 3/22/2024 | OK to Issue CofO | DAVID SCANTLIN |