4916 E LINCOLN AVE 90042
Certificate Information: 4916 E LINCOLN AVE 90042
- Application / Permit
- 22014-20000-05656
- Plan Check / Job No.
- B22VN17057
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 17'-1" X 19'-2" AND INTERIOR REMODEL TO AN (E) S.F.D . WORK DONE PER ENGINEER.
- Permit Issued
- Issued on 1/12/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2022 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 11/22/2022 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 11/22/2022 | MIROOSH KHACHATOORIAN |
| Building Plans Picked Up | 11/29/2022 | APPLICANT |
| Applicant returned to address corrections | 12/29/2022 | ALFRED RAMIREZ |
| Issued | 1/12/2023 | APPLICANT |
| CofO in Progress | 8/17/2023 | BRIAN SULLIVAN |
| CofO Issued | 8/17/2023 | RONALD MYRICK |
| Permit Finaled | 8/17/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/22/2022 | LUCIA MERCADO |
| Eng Process Fee Ord 176,300 | Cleared | 12/28/2022 | LUCIA MERCADO |
| Public Works-Highway Ded. | Cleared | 12/28/2022 | LUCIA MERCADO |
| Public Works-Open Permits | Cleared | 12/28/2022 | LUCIA MERCADO |
| Public Works-Sewers | Cleared | 12/28/2022 | LUCIA MERCADO |
| Grading Pre-Inspection | Cleared | 12/29/2022 | KIRK LINKLATER |
Contact Information
| Contractor | My Home Builders Inc; Lic. No.: 1002927-B | 20720 VENTURA BLVD #280 WOODLAND HILLS, CA 91364 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/19/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 4/24/2023 | Conditional Approval | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 4/24/2023 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 5/22/2023 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 5/22/2023 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2023 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 5/22/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 5/22/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 6/6/2023 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 6/6/2023 | Approved | CHARLES BOGHOSKHAN |
| PLUMBING-Rough | 6/6/2023 | Partial Approval | CHARLES BOGHOSKHAN |
| BUILDING-Rough-Frame | 6/9/2023 | Partial Approval | JEFFREY MEAD |
| Insulation | 6/9/2023 | Corrections Issued | JEFFREY MEAD |
| Drywall Nailing | 6/16/2023 | Conditional Approval | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 6/28/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 8/9/2023 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 8/9/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 8/9/2023 | Approved | CRAIG VAUGHAN |
| Final | 8/9/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 8/9/2023 | Approved | CRAIG VAUGHAN |
| Green Building Final | 8/9/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 8/9/2023 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 8/9/2023 | SGSOV Not Ready | CRAIG VAUGHAN |
| Smoke Detectors | 8/9/2023 | Approved | CRAIG VAUGHAN |
| Final | 8/16/2023 | OK to Issue CofO | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 8/16/2023 | SGSOV Approved | BRIAN SULLIVAN |