20344 W ROSCOE BLVD 91306
Certificate Information: 20344 W ROSCOE BLVD 91306
- Application / Permit
- 22014-20000-05647
- Plan Check / Job No.
- B22VN17017
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* CONVERT (E) DEATCHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT AND ADDITION (171 SF) PER LAMC 12.22.A.33(c)-(d).
- Permit Issued
- Issued on 12/30/2022
- Issuing Office
- Current Status
- CofO Issued on 5/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/23/2022 | VIVIAN LAO |
| Corrections Issued | 11/28/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 12/27/2022 | SELLA BENYAMIN |
| Plan Check Approved | 12/30/2022 | SELLA BENYAMIN |
| Issued | 12/30/2022 | APPLICANT |
| CofO in Progress | 4/4/2024 | ALEXANDER HANDY |
| Permit Finaled | 5/14/2024 | JOHN JANSON |
| CofO Issued | 5/14/2024 | JOHN JANSON |
| Permit Finaled | 5/14/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/29/2022 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 11/29/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/30/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 11/30/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 11/30/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 11/30/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 11/30/2022 | MEGAN GODINEZ |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/7/2023 | Partial Approval | ALEXANDER HANDY |
| Sewer | 11/7/2023 | Approved | ALEXANDER HANDY |
| Deputy Drilled-In Anchors | 11/8/2023 | Conditional Approval | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 11/9/2023 | Approved | ALEXANDER HANDY |
| Wood Frame | 11/20/2023 | Partial Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 11/28/2023 | Partial Approval | ALEXANDER HANDY |
| Green Building Rough | 11/28/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 12/26/2023 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 12/26/2023 | Approved | ALEXANDER HANDY |
| Green Building Rough | 12/26/2023 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 12/26/2023 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 12/26/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 12/26/2023 | Approved | ALEXANDER HANDY |
| Shower Pan | 12/26/2023 | Approved | ALEXANDER HANDY |
| Special/Order Compliance | 12/26/2023 | Corrections Issued | ALEXANDER HANDY |
| Insulation | 1/3/2024 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 1/8/2024 | Approved | ALEXANDER HANDY |
| Shower Pan | 1/8/2024 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 1/8/2024 | Approved | ALEXANDER HANDY |
| Final | 3/27/2024 | Corrections Issued | ALEXANDER HANDY |
| Footing/Foundation/Slab | 3/27/2024 | Approved | ALEXANDER HANDY |
| Green Building Final | 3/27/2024 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 3/27/2024 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 3/27/2024 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 4/4/2024 | Approved | ALEXANDER HANDY |
| Final | 4/4/2024 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 4/4/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 4/4/2024 | Approved | ALEXANDER HANDY |