4305 N BAKMAN AVE 91602
Certificate Information: 4305 N BAKMAN AVE 91602
- Application / Permit
- 22014-20000-05610
- Plan Check / Job No.
- B22VN16878
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: REMOVE PORTION (E) DETACHED STORAGE AND CONVERT WITH (N) IRREGULAR SHAPED ADDITION OF 19'-3" x 16'-7" INTO A (N) DETACHED 19'-3" x 16'-7" ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33 (c) AND (d) PER ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 6/6/2023
- Issuing Office
- Current Status
- CofO Issued on 7/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2022 | LUISANGEL VALENZUELA |
| Corrections Issued | 11/18/2022 | LUISANGEL VALENZUELA |
| Plan Check Approved | 6/6/2023 | ALFRED RAMIREZ |
| Issued | 6/6/2023 | APPLICANT |
| CofO in Progress | 7/8/2024 | CHRISTOPHER ROJAS |
| Permit Finaled | 7/24/2024 | RUBEN SALAS |
| CofO Issued | 7/24/2024 | RUBEN SALAS |
| Permit Finaled | 7/24/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/8/2023 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 2/8/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/9/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2023 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 5/30/2023 | RIDWAN HARDY |
Contact Information
| Architect | Gemigniani,, Richard Louis; Lic. No.: NA18783 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/28/2023 | Approved | CHRISTOPHE COCHRAN |
| Pre-Inspection | 8/1/2023 | Corrections Issued | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 9/8/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2023 | Approved | RYAN SALAZAR |
| Footing/Foundation/Slab | 9/15/2023 | Approved | RYAN SALAZAR |
| Insulation | 9/22/2023 | Corrections Issued | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 10/26/2023 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 10/26/2023 | Corrections Issued | JUAN VALENZUELA |
| HVAC-Rough | 10/26/2023 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Rough | 10/26/2023 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 1/25/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 2/7/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 2/15/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| HVAC-Rough | 2/15/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 2/21/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 2/21/2024 | Partial Approval | KIRK SANDERS |
| HVAC-Rough | 2/21/2024 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 3/1/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 3/1/2024 | Approved | KIRK SANDERS |
| HVAC-Rough | 3/1/2024 | Corrections Issued | KIRK SANDERS |
| Insulation | 3/1/2024 | Corrections Issued | KIRK SANDERS |
| Drywall Nailing | 3/28/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 3/28/2024 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 3/28/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 6/21/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 6/21/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 6/21/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 6/21/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 7/2/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 7/2/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |