11017 W CALIFA ST 91601
Certificate Information: 11017 W CALIFA ST 91601
- Application / Permit
- 22014-20000-05589
- Plan Check / Job No.
- B22VN16816
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 27' 5" X 15' IRR-SHAPE REAR ADDITION TO (E) SFD. ALL WORK DONER PER ENGINEERING.
- Permit Issued
- Issued on 5/5/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2022 | HAYATO TSUCHIYA |
| Corrections Issued | 11/14/2022 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 11/16/2022 | APPLICANT |
| Applicant returned to address corrections | 1/26/2023 | GURUNATH NESARAJAH |
| Plan Check Approved | 5/5/2023 | VICTOR CHEN |
| Issued | 5/5/2023 | APPLICANT |
| CofO in Progress | 8/29/2023 | JOHN HAYES |
| Permit Finaled | 10/13/2023 | RUBEN SALAS |
| CofO Issued | 10/13/2023 | RUBEN SALAS |
| Permit Finaled | 10/13/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/13/2023 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2023 | FERNANDO GIL |
| Public Works-Highway Ded. | Cleared | 5/4/2023 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 5/4/2023 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 5/4/2023 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chu,, Tien Manh; Lic. No.: C72324 | 9542 PACIFIC AVE ANAHEIM, CA 92804 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/15/2023 | Not Ready for Inspection | JOHN HAYES |
| Pre-Inspection | 5/15/2023 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 5/19/2023 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 5/19/2023 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 5/30/2023 | Partial Approval | JOHN HAYES |
| Footing/Foundation/Slab | 6/7/2023 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2023 | Partial Approval | RYAN SALAZAR |
| Insulation | 6/21/2023 | Partial Approval | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2023 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 7/11/2023 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 7/11/2023 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2023 | Partial Approval | JOHN HAYES |
| Green Building Rough | 7/11/2023 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 7/11/2023 | Approved | JOHN HAYES |
| PLUMBING-Rough | 7/11/2023 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 7/11/2023 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 7/13/2023 | Approved | JOHN HAYES |
| Green Building Rough | 7/13/2023 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 7/13/2023 | Approved | JOHN HAYES |
| Insulation | 7/17/2023 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 7/17/2023 | Corrections Issued | JOHN HAYES |
| Shower Pan | 7/17/2023 | Approved | JOHN HAYES |
| Insulation | 7/19/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 7/19/2023 | Approved | JOHN HAYES |
| Drywall Nailing | 7/24/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 7/24/2023 | Approved | JOHN HAYES |
| Final | 8/21/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 8/21/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 8/21/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 8/21/2023 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 8/21/2023 | Approved | JENNIFER RABUCHIN |
| Final | 8/28/2023 | OK to Issue CofO | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 8/28/2023 | SGSOV Approved | JOHN HAYES |