11017 W CALIFA ST 91601

Certificate Information: 11017 W CALIFA ST 91601

Application / Permit
22014-20000-05589
Plan Check / Job No.
B22VN16816
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
27' 5" X 15' IRR-SHAPE REAR ADDITION TO (E) SFD. ALL WORK DONER PER ENGINEERING.
Permit Issued
Issued on 5/5/2023
Issuing Office
Metro
Current Status
CofO Issued on 10/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/14/2022 APPLICANT
Assigned to Plan Check Engineer 11/14/2022 HAYATO TSUCHIYA
Corrections Issued 11/14/2022 HAYATO TSUCHIYA
Building Plans Picked Up 11/16/2022 APPLICANT
Applicant returned to address corrections 1/26/2023 GURUNATH NESARAJAH
Plan Check Approved 5/5/2023 VICTOR CHEN
Issued 5/5/2023 APPLICANT
CofO in Progress 8/29/2023 JOHN HAYES
Permit Finaled 10/13/2023 RUBEN SALAS
CofO Issued 10/13/2023 RUBEN SALAS
Permit Finaled 10/13/2023 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/13/2023 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 4/20/2023 FERNANDO GIL
Public Works-Highway Ded. Cleared 5/4/2023 MEGAN GODINEZ
Public Works-Open Permits Cleared 5/4/2023 MEGAN GODINEZ
Public Works-Sewers Cleared 5/4/2023 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Chu,, Tien Manh; Lic. No.: C72324 9542 PACIFIC AVE      ANAHEIM, CA 92804

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/15/2023 Not Ready for Inspection JOHN HAYES
Pre-Inspection 5/15/2023 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 5/19/2023 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 5/19/2023 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 5/30/2023 Partial Approval JOHN HAYES
Footing/Foundation/Slab 6/7/2023 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/14/2023 Partial Approval RYAN SALAZAR
Insulation 6/21/2023 Partial Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 6/27/2023 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 7/11/2023 Partial Approval JOHN HAYES
ELECTRICAL-Rough 7/11/2023 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 7/11/2023 Partial Approval JOHN HAYES
Green Building Rough 7/11/2023 Not Ready for Inspection JOHN HAYES
HVAC-Rough 7/11/2023 Approved JOHN HAYES
PLUMBING-Rough 7/11/2023 Not Ready for Inspection JOHN HAYES
Wood Frame 7/11/2023 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 7/13/2023 Approved JOHN HAYES
Green Building Rough 7/13/2023 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 7/13/2023 Approved JOHN HAYES
Insulation 7/17/2023 Not Ready for Inspection JOHN HAYES
Interior/Exterior Lathing 7/17/2023 Corrections Issued JOHN HAYES
Shower Pan 7/17/2023 Approved JOHN HAYES
Insulation 7/19/2023 Approved JOHN HAYES
Interior/Exterior Lathing 7/19/2023 Approved JOHN HAYES
Drywall Nailing 7/24/2023 Approved JOHN HAYES
Interior/Exterior Lathing 7/24/2023 Approved JOHN HAYES
Final 8/21/2023 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 8/21/2023 Approved JENNIFER RABUCHIN
Green Building Final 8/21/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 8/21/2023 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 8/21/2023 Approved JENNIFER RABUCHIN
Final 8/28/2023 OK to Issue CofO JOHN HAYES
SGSOV-Seismic Gas S/O Valve 8/28/2023 SGSOV Approved JOHN HAYES