8124 W APPERSON ST 91040

Certificate Information: 8124 W APPERSON ST 91040

Application / Permit
22014-20000-05586
Plan Check / Job No.
B22VN16810
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN*** 21'-3" X 21'-9" ADDTION TO AND CONVERT EXISTING 18'-0" X 20'-0" DETACHED GARAGE INTO AND ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)) - ALL WORK PER WFPP ***COMPLY WITH DEPARTMENT ORDER effective date 05/06/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 2/24/2023
Issuing Office
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/14/2022 APPLICANT
Assigned to Plan Check Engineer 11/18/2022 DANIEL ABRAMYAN
Corrections Issued 11/20/2022 DANIEL ABRAMYAN
Plan Check Approved 2/23/2023 DANIEL ABRAMYAN
Issued 2/24/2023 APPLICANT
CofO in Progress 3/9/2024 DAVID ANDERSON
Permit Finaled 3/29/2024 DANIEL ORRANTE
CofO Issued 3/29/2024 DANIEL ORRANTE
Permit Finaled 3/29/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/6/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 12/6/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 12/12/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 12/12/2022 DAGOVERTO GUERRERO
Construction near power lines Cleared 1/28/2023 RIDWAN HARDY
Construction within easement Cleared 1/28/2023 RIDWAN HARDY
Grading Pre-Inspection Cleared 2/7/2023 KIRK LINKLATER
GPI Written Notices Cleared 2/23/2023 DANIEL ABRAMYAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 3/8/2023 Approved DAVID ANDERSON
Underground Mechanical 3/8/2023 Partial Approval DAVID ANDERSON
PLUMBING-Rough 4/14/2023 Partial Approval DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 5/1/2023 Approved DAVID ANDERSON
Footing/Foundation/Slab 5/1/2023 Approved DAVID ANDERSON
BUILDING-Rough-Frame 7/13/2023 Not Ready for Inspection DAVID ANDERSON
ELECTRICAL-Rough 7/13/2023 Approved DAVID ANDERSON
HVAC-Rough 7/13/2023 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 7/13/2023 Approved DAVID ANDERSON
Wood Frame 7/13/2023 Not Ready for Inspection DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 8/1/2023 Approved WILLIAM WREN
Wood Frame 8/1/2023 Not Ready for Inspection WILLIAM WREN
HVAC-Rough 8/31/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 8/31/2023 Approved DAVID ANDERSON
Insulation 12/18/2023 Corrections Issued DAVID ANDERSON
Drywall Nailing 1/8/2024 Approved DAVID ANDERSON
Shower Pan 1/8/2024 Approved DAVID ANDERSON
Interior/Exterior Lathing 1/17/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 3/4/2024 Approved DAVID ANDERSON
Final 3/4/2024 Corrections Issued DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 3/4/2024 SGSOV Not Ready DAVID ANDERSON
Smoke Detectors 3/4/2024 Approved DAVID ANDERSON
Final 3/8/2024 OK to Issue CofO DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 3/8/2024 SGSOV Approved DAVID ANDERSON