10859 W WALNUT DR 91040

Certificate Information: 10859 W WALNUT DR 91040

Application / Permit
22014-20000-05571
Plan Check / Job No.
B22VN16789
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE MOST OF INT. AND EXT. WALLS AND ERECT AN IRR. SHAPED 101'-2" x 119'-6 3/4" ONE-STORY SINGLE FAMILY DWELLING W/ ATT. PATIO COVER, GARAGE (7-CAR) AND STORAGE; NFPA-13D THRU-OUT
Permit Issued
Issued on 8/31/2023
Issuing Office
Current Status
CofO Issued on 12/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2022 APPLICANT
Assigned to Plan Check Engineer 12/15/2022 SEAN SHAHMIRI
Corrections Issued 12/20/2022 SEAN SHAHMIRI
Quality Review Completed 12/22/2022 OMID HEDAYAT
Applicant returned to address corrections 2/7/2023 SEAN SHAHMIRI
Plan Check Approved 8/30/2023 SEAN SHAHMIRI
Issued 8/31/2023 APPLICANT
CofO in Progress 11/20/2024 DAVID ANDERSON
Permit Finaled 12/17/2024 RUBEN SALAS
CofO Issued 12/17/2024 RUBEN SALAS
Permit Finaled 12/17/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/3/2023 LEE GUILBEAUX
Grading Pre-Inspection Cleared 1/3/2023 ROBERT HUGHES
Hydrant and Access approval Cleared 2/10/2023 RUEL COLE
Miscellaneous Cleared 5/4/2023 DANIEL CORONADO
Specific Plan Cleared 5/4/2023 DANIEL CORONADO
Low Impact Development Cleared 6/23/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 7/24/2023 MEGAN GODINEZ
Private sewage disp. approval Cleared 8/24/2023 DAN RYAN EVANGELISTA

Contact Information

Contractor Owner-Builder       ,
Engineer Roberts,, Jeffrey Allan; Lic. No.: NA56881       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/7/2023 Partial Approval DAVID ANDERSON
Deputy Drilled-In Anchors 9/15/2023 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 9/26/2023 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 1/24/2024 Partial Approval DAVID ANDERSON
BUILDING-Rough-Frame 4/5/2024 Corrections Issued DAVID ANDERSON
ELECTRICAL-Rough 4/5/2024 Corrections Issued DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 4/5/2024 Corrections Issued DAVID ANDERSON
Green Building Rough 4/5/2024 Approved DAVID ANDERSON
HVAC-Rough 4/5/2024 Approved DAVID ANDERSON
PLUMBING-Rough 4/5/2024 Approved DAVID ANDERSON
Deputy Wood Construction 4/12/2024 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 4/30/2024 Partial Approval DAVID ANDERSON
ELECTRICAL-Rough 4/30/2024 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 4/30/2024 Approved DAVID ANDERSON
BUILDING-Rough-Frame 5/20/2024 Approved DAVID ANDERSON
Insulation 5/20/2024 Approved DAVID ANDERSON
Interior/Exterior Lathing 5/20/2024 Partial Approval DAVID ANDERSON
Drywall Nailing 5/24/2024 Partial Approval DAVID ANDERSON
Drywall Nailing 5/29/2024 Approved DAVID ANDERSON
Interior/Exterior Lathing 6/6/2024 Approved DAVID ANDERSON
Underground Mechanical 8/23/2024 Partial Approval DAVID ANDERSON
Final 9/13/2024 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 9/13/2024 Approved DAVID ANDERSON
Green Building Final 9/13/2024 Not Ready for Inspection DAVID ANDERSON
Final 11/19/2024 OK to Issue CofO DAVID ANDERSON
Green Building Final 11/19/2024 Approved DAVID ANDERSON