12503 W EMELITA ST 91607
Certificate Information: 12503 W EMELITA ST 91607
- Application / Permit
- 22014-20000-05540
- Plan Check / Job No.
- B22VN16678
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 11'-9" x 15'8" ADDITION TO EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 2/27/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/1/2022 | SELLA BENYAMIN |
| Corrections Issued | 12/8/2022 | SELLA BENYAMIN |
| Quality Review Completed | 12/16/2022 | STEVEN KIM |
| Building Plans Picked Up | 12/16/2022 | APPLICANT |
| Applicant returned to address corrections | 1/20/2023 | SELLA BENYAMIN |
| Plan Check Approved | 2/24/2023 | SELLA BENYAMIN |
| Issued | 2/27/2023 | APPLICANT |
| CofO in Progress | 9/18/2023 | SCOTT SHUSTER |
| CofO in Progress | 9/18/2023 | SCOTT SHUSTER |
| Permit Finaled | 12/29/2023 | DAVID JAMES |
| CofO Issued | 12/29/2023 | DAVID JAMES |
| Permit Finaled | 12/29/2023 | DAVID JAMES |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/21/2022 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 12/21/2022 | COLIN LOREDO |
| Address approval | Cleared | 2/10/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/10/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/13/2023 | Approved | BRYAN MEYER |
| Footing/Foundation/Slab | 5/4/2023 | Partial Approval | BRYAN MEYER |
| Footing/Foundation/Slab | 5/8/2023 | Approved | BRYAN MEYER |
| BUILDING-Rough-Frame | 5/17/2023 | Partial Inspection | BRYAN MEYER |
| Green Building Rough | 5/17/2023 | Not Ready for Inspection | BRYAN MEYER |
| Insulation | 5/22/2023 | Approved | BRYAN MEYER |
| ELECTRICAL-Rough | 5/24/2023 | Approved | BRYAN MEYER |
| Drywall Nailing | 5/31/2023 | Approved | THOMAS WOODS |
| Interior/Exterior Lathing | 5/31/2023 | Approved | THOMAS WOODS |
| ELECTRICAL-Final | 8/10/2023 | Not Ready for Inspection | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 9/1/2023 | Approved | SCOTT SHUSTER |
| Final | 9/1/2023 | Partial Inspection | SCOTT SHUSTER |
| Green Building Final | 9/1/2023 | Approved | SCOTT SHUSTER |
| Green Building Rough | 9/1/2023 | Approved | SCOTT SHUSTER |
| SGSOV-Seismic Gas S/O Valve | 9/1/2023 | SGSOV Not Ready | SCOTT SHUSTER |
| Smoke Detectors | 9/1/2023 | Partial Inspection | SCOTT SHUSTER |
| Final | 9/12/2023 | Partial Inspection | SCOTT SHUSTER |
| SGSOV-Seismic Gas S/O Valve | 9/12/2023 | SGSOV Approved | SCOTT SHUSTER |
| Smoke Detectors | 9/12/2023 | Partial Approval | SCOTT SHUSTER |
| Final | 9/15/2023 | OK to Issue CofO | SCOTT SHUSTER |
| Rough-Elec/Plmb/HVAC | 9/15/2023 | Approved | SCOTT SHUSTER |
| Smoke Detectors | 9/15/2023 | Approved | SCOTT SHUSTER |