6501 N SAUSALITO AVE 91307
Certificate Information: 6501 N SAUSALITO AVE 91307
- Application / Permit
- 22014-20000-05508
- Plan Check / Job No.
- B22VN16564
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 18'-1" X 25'-0" IRREGULAR SHAPED ADDITION FOR NEW BEDROOM, BATHROOM, AND CLOSET
- Permit Issued
- Issued on 2/14/2023
- Issuing Office
- Valley
- Current Status
- CofO Corrected on 11/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2022 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 11/7/2022 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 2/14/2023 | PINANK PATEL |
| Issued | 2/14/2023 | APPLICANT |
| CofO in Progress | 10/26/2023 | TROY SANDERS |
| Re-Activate Permit | 11/17/2023 | JOHN JANSON |
| CofO Issued-Status Void | 11/17/2023 | JOHN JANSON |
| Permit Finaled-Status Void | 11/17/2023 | JOHN JANSON |
| CofO Corrected | 11/17/2023 | JOHN JANSON |
| Permit Finaled | 11/17/2023 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/9/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/10/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 11/10/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 11/10/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 11/10/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 11/10/2022 | MEGAN GODINEZ |
| Construction within easement | Cleared | 1/28/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/5/2023 | Partial Approval | TROY SANDERS |
| Deputy Drilled-In Anchors | 7/25/2023 | Conditional Approval | TROY SANDERS |
| Footing/Foundation/Slab | 7/26/2023 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 8/8/2023 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2023 | Partial Approval | TROY SANDERS |
| Green Building Rough | 8/8/2023 | Not Ready for Inspection | TROY SANDERS |
| ELECTRICAL-Rough | 8/31/2023 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2023 | Approved | TROY SANDERS |
| HVAC-Rough | 8/31/2023 | Approved | TROY SANDERS |
| PLUMBING-Rough | 8/31/2023 | Approved | TROY SANDERS |
| Green Building Rough | 9/6/2023 | Approved | TROY SANDERS |
| Insulation | 9/6/2023 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 9/6/2023 | Approved | TROY SANDERS |
| Shower Pan | 9/6/2023 | Approved | TROY SANDERS |
| Drywall Nailing | 9/13/2023 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 10/25/2023 | Approved | TROY SANDERS |
| Final | 10/25/2023 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 10/25/2023 | Approved | TROY SANDERS |
| HVAC-Final | 10/25/2023 | Approved | TROY SANDERS |
| PLUMBING-Final | 10/25/2023 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 10/25/2023 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 10/25/2023 | Approved | TROY SANDERS |