144 E AVENUE 32 90031
Certificate Information: 144 E AVENUE 32 90031
- Application / Permit
- 22014-20000-05503
- Plan Check / Job No.
- B22VN16547
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) FRONT PATIO AND INTERIOR REMODEL TO EXISTING SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 12/1/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2022 | PINANK PATEL |
| Corrections Issued | 11/7/2022 | PINANK PATEL |
| Applicant returned to address corrections | 11/22/2022 | EDWIN ESPIN |
| Applicant returned to address corrections | 11/28/2022 | VICTOR CHEN |
| Plan Check Approved | 12/1/2022 | FERNANDO FLORES |
| Issued | 12/1/2022 | APPLICANT |
| CofO in Progress | 5/31/2023 | AMY COLIN |
| Permit Finaled | 6/29/2023 | DEROLD HAUFF |
| CofO Issued | 6/29/2023 | DEROLD HAUFF |
| Permit Finaled | 6/29/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2022 | OSCAR GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 11/22/2022 | OSCAR GUTIERREZ |
| CPC | Cleared | 11/29/2022 | DAMIAN GATTO |
| HPOZ | Cleared | 11/29/2022 | DAMIAN GATTO |
| ZI | Cleared | 11/29/2022 | DAMIAN GATTO |
Contact Information
| Contractor | Reliance Development And Construction Inc; Lic. No.: 1061538-B | 5312 ATLANTIC BLVD MAYWOOD, CA 90270 |
| Engineer | Keshishian,, Nejdeh; Lic. No.: C38341 | 2654 RISA DR GLENDALE, CA 91208 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/19/2022 | Corrections Issued | AMY COLIN |
| Excavation/Setback/Form/Re-Bar | 12/21/2022 | Corrections Issued | AMY COLIN |
| Excavation/Setback/Form/Re-Bar | 12/22/2022 | Partial Approval | AMY COLIN |
| Footing/Foundation/Slab | 12/30/2022 | Corrections Issued | AMY COLIN |
| Wood Frame | 1/24/2023 | Not Ready for Inspection | AMY COLIN |
| Wood Frame | 2/3/2023 | Corrections Issued | JEFFREY MEAD |
| BUILDING-Rough-Frame | 2/7/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 2/7/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Wood Frame | 2/7/2023 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2023 | Corrections Issued | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 2/17/2023 | Partial Approval | AMY COLIN |
| Green Building Rough | 2/17/2023 | Not Ready for Inspection | AMY COLIN |
| Wood Frame | 2/17/2023 | Partial Approval | AMY COLIN |
| Wood Frame | 2/21/2023 | Corrections Issued | AMY COLIN |
| Wood Frame | 2/24/2023 | Corrections Issued | AMY COLIN |
| Wood Frame | 3/6/2023 | Partial Approval | AMY COLIN |
| Drywall Nailing | 3/10/2023 | Approved | AMY COLIN |
| ELECTRICAL-Rough | 3/10/2023 | Approved | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2023 | Corrections Issued | AMY COLIN |
| Insulation | 3/10/2023 | Approved | AMY COLIN |
| BUILDING-Rough-Frame | 5/15/2023 | Approved | AMY COLIN |
| Final | 5/15/2023 | Corrections Issued | AMY COLIN |
| Footing/Foundation/Slab | 5/15/2023 | Approved | AMY COLIN |
| Green Building Final | 5/15/2023 | Approved | AMY COLIN |
| Green Building Rough | 5/15/2023 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 5/15/2023 | SGSOV Approved | AMY COLIN |
| Smoke Detectors | 5/15/2023 | Approved | AMY COLIN |
| Final | 5/31/2023 | OK to Issue CofO | AMY COLIN |