11960 N DORAL AVE 91326
Certificate Information: 11960 N DORAL AVE 91326
- Application / Permit
- 22014-20000-05500
- Plan Check / Job No.
- B22VN16542
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 681 SQFT ADDITION TO FRONT AND BACK OF (E) 2 STORY SINGLE FAMILY DWELLING INCLUDING NEW BEDROOM AND MASTER BEDROOM W/REMODELING (E) BEDROOMS AND KICHEN/STAIRS
- Permit Issued
- Issued on 3/29/2023
- Issuing Office
- Valley
- Current Status
- Issued on 3/29/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2022 | PETER MOSESIAN |
| Corrections Issued | 11/16/2022 | PETER MOSESIAN |
| Quality Review Completed | 11/17/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 11/18/2022 | APPLICANT |
| Applicant returned to address corrections | 2/14/2023 | PETER MOSESIAN |
| Plan Check Approved | 3/29/2023 | PETER MOSESIAN |
| Issued | 3/29/2023 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 2/21/2023 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 2/21/2023 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 2/21/2023 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 2/21/2023 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 2/21/2023 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 2/21/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/21/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2023 | DAGOVERTO GUERRERO |
| ZA Case | Cleared | 3/7/2023 | DANIEL CORONADO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/16/2023 | Corrections Issued | SEAN WIRCH |
| Footing/Foundation/Slab | 5/19/2023 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 5/19/2023 | Approved | DAVID SCANTLIN |
| Special/Order Compliance | 7/19/2023 | Corrections Issued | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | Partial Approval | STEVEN BACK |
| Deputy Wood Construction | 2/16/2024 | Conditional Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 4/3/2024 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 4/3/2024 | Not Ready for Inspection | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2024 | Approved | STEVEN BACK |
| HVAC-Rough | 4/3/2024 | Approved | STEVEN BACK |
| PLUMBING-Rough | 4/3/2024 | Approved | STEVEN BACK |
| Sewer | 4/3/2024 | Approved | STEVEN BACK |
| Shower Pan | 4/3/2024 | Approved | STEVEN BACK |
| Special/Order Compliance | 4/3/2024 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 5/2/2024 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 5/2/2024 | Approved | JEFFREY PARD |
| Green Building Rough | 5/2/2024 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 5/2/2024 | Approved | JEFFREY PARD |
| Insulation | 7/3/2024 | Approved | JEFFREY PARD |
| Drywall Nailing | 7/30/2024 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 7/30/2024 | Partial Inspection | ARUTYUN MADATYAN |
| Final | 4/7/2026 | Corrections Issued | STEVEN BACK |
| Green Building Final | 4/7/2026 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 4/7/2026 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 4/7/2026 | Corrections Issued | STEVEN BACK |
| Final | 5/13/2026 | Corrections Issued | STEVEN BACK |
| Smoke Detectors | 5/13/2026 | Corrections Issued | STEVEN BACK |