5234 1/2 N VINCENT AVE 90041

Certificate Information: 5234 1/2 N VINCENT AVE 90041

Application / Permit
22014-20000-05481
Plan Check / Job No.
B22VN16501
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 10'-0" x 16'-0" ADDITION TO AND CONVERT (E) DETACHED GARAGE INTO A NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 3/16/2023
Issuing Office
Metro
Current Status
CofO Issued on 3/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2022 APPLICANT
Assigned to Plan Check Engineer 11/7/2022 ARTIN ZARUKIAN
Corrections Issued 11/8/2022 ARTIN ZARUKIAN
Building Plans Picked Up 11/10/2022 APPLICANT
Plan Check Approved 12/2/2022 SARKIS HARABEDIAN
Issued 3/16/2023 APPLICANT
CofO in Progress 3/1/2024 CRAIG VAUGHAN
Permit Finaled 3/4/2024 DEROLD HAUFF
Permit Finaled 3/4/2024 DEROLD HAUFF
CofO Issued 3/4/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/14/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 11/14/2022 JEANIE LAM
Grading Pre-Inspection Cleared 11/18/2022 VASIL MIHALEV
Sewer availability Cleared 11/18/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 11/21/2022 JEANIE LAM

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Lord'S Construction; Lic. No.: 854236-B 15364 NARANJA AVERNUE      PARAMOUNT, CA 90723

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/10/2023 Approved CRAIG VAUGHAN
PLUMBING-Rough 4/20/2023 Partial Approval LILIANA PORTILLO
Underground Mechanical 4/20/2023 Partial Approval LILIANA PORTILLO
BUILDING-Rough-Frame 6/27/2023 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 6/27/2023 Approved BRIAN SULLIVAN
Green Building Rough 6/27/2023 Approved BRIAN SULLIVAN
HVAC-Rough 6/27/2023 Conditional Approval BRIAN SULLIVAN
PLUMBING-Rough 6/27/2023 Approved BRIAN SULLIVAN
Insulation 7/24/2023 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 7/24/2023 Partial Approval CRAIG VAUGHAN
Drywall Nailing 8/3/2023 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 8/3/2023 Approved CRAIG VAUGHAN
Shower Pan 8/3/2023 Approved CRAIG VAUGHAN
Final 10/25/2023 Corrections Issued CRAIG VAUGHAN
Green Building Final 10/25/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 10/25/2023 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 10/25/2023 Approved CRAIG VAUGHAN
Final 12/19/2023 No Access for Inspection BRENDAN MORELLI
Final 1/5/2024 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Final 2/29/2024 Approved CRAIG VAUGHAN
Final 2/29/2024 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 2/29/2024 Approved CRAIG VAUGHAN
PLUMBING-Final 2/29/2024 Approved CRAIG VAUGHAN