2174 N BANYAN DR 90049
Certificate Information: 2174 N BANYAN DR 90049
- Application / Permit
- 22014-20000-05476
- Plan Check / Job No.
- B22VN16489
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR INTERIOR REMODEL INCLUDING NEW EXTERIOR WALLS/INTERIOR WALLS AND RELOCATING KITCHEN/LIVING AREA AND REROOFING ENTIRE ROOF, REMOVE EXISTING PATIO COVER AND BUILD NEW (612 SQFT) PATIO COVER W/ (19'-0"x13'-0"),247 SQFT MASTER BEDROOM ADDITION W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 7/18/2024
- Issuing Office
- Current Status
- Issued on 7/18/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/1/2022 | PETER MOSESIAN |
| Corrections Issued | 12/9/2022 | PETER MOSESIAN |
| Quality Review Completed | 12/14/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 12/19/2022 | APPLICANT |
| Plan Check Approved | 7/12/2024 | PETER MOSESIAN |
| Issued | 7/18/2024 | APPLICANT |
Permit Application Clearance Information
| Watercourse | Cleared | 1/5/2023 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 1/10/2023 | JASON NG |
| BHO/Hillside ordinance | Cleared | 1/11/2023 | JASON NG |
| BHO/Hillside ordinance | Cleared | 1/11/2023 | JASON NG |
| BHO/Hillside ordinance | Cleared | 1/11/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 2/15/2024 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 2/17/2024 | LIAM ODONOVAN |
| Low Impact Development | Cleared | 7/8/2024 | VICTOR MENDOZA |
| Roof/Waste drainage to street | Cleared | 7/11/2024 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Ceilbright Services Inc; Lic. No.: 957706-B | 9230 W OLYMPIC BLVD BEVERLY HILLS, CA 90212 |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Engineer | Liston,, Leonard Irvin; Lic. No.: C93123 | 889 PIERCE COURT, SUITE 101 THOUSAND OAKS, CA 91360 |
| Engineer | Naraghi-Arani,, Kamran; Lic. No.: C40985 | 30423 CANWOOD ST STE 223 AGOURA HILLS, CA 91301 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/19/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 9/25/2024 | Conditional Approval | EVAN COOPER |
| Footing/Foundation/Slab | 10/1/2024 | Partial Approval | KEVIN SARGSYAN |
| Piling/Pier/Caisson | 10/1/2024 | Approved | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 10/4/2024 | Conditional Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 10/30/2024 | Corrections Issued | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 10/31/2024 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 11/1/2024 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 11/5/2024 | Partial Approval | ARAM AVEDISIAN |
| Deputy Reinf. Concrete | 11/6/2024 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 11/15/2024 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 11/20/2024 | Approved | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 12/9/2024 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 1/31/2025 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2025 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2025 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 4/1/2025 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 5/19/2025 | Corrections Issued | KEVIN SARGSYAN |
| FLOOD-Proofing Certificate | 5/19/2025 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 5/28/2025 | Partial Approval | KEVIN SARGSYAN |
| HVAC-Rough | 6/2/2025 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 6/24/2025 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2025 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 7/1/2025 | Approved | KEVIN SARGSYAN |
| Deputy Wood Construction | 7/3/2025 | Conditional Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2025 | Approved | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 8/21/2025 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 10/15/2025 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 10/17/2025 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 10/17/2025 | Approved | KEVIN SARGSYAN |
| Insulation | 10/28/2025 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 11/12/2025 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 3/11/2026 | Approved | KEVIN SARGSYAN |