8120 N OAKDALE AVE 91306
Certificate Information: 8120 N OAKDALE AVE 91306
- Application / Permit
- 22014-20000-05466
- Plan Check / Job No.
- B22VN16467
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION OF 28' x 30'-6" ACCESSORY DWELLING UNIT (798 SQFT) TO (E) REC ROOM PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)1, (d)1, and (g). REC ROOM TO REMAIN. WORK DONE PER ENGINEER.
- Permit Issued
- Issued on 4/13/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2022 | ISIS ARGUETA |
| Corrections Issued | 11/9/2022 | ISIS ARGUETA |
| Building Plans Picked Up | 11/10/2022 | APPLICANT |
| Applicant returned to address corrections | 1/17/2023 | SERGIO MUNIZ |
| Plan Check Approved | 4/12/2023 | MIROOSH KHACHATOORIAN |
| Issued | 4/13/2023 | APPLICANT |
| CofO in Progress | 1/26/2024 | ALEXANDER HANDY |
| Permit Finaled | 2/15/2024 | JOHN JANSON |
| CofO Issued | 2/15/2024 | JOHN JANSON |
| Permit Finaled | 2/15/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/24/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/13/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 3/17/2023 | MEGAN GODINEZ |
| ZA Case | Cleared | 3/22/2023 | NATHAN ROMINE |
| ZA Case | Cleared | 3/22/2023 | NATHAN ROMINE |
| Low Impact Development | Cleared | 3/28/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 4/1/2023 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/8/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 6/26/2023 | Partial Approval | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 6/29/2023 | Approved | HORACE FULTZ |
| Footing/Foundation/Slab | 6/29/2023 | Approved | HORACE FULTZ |
| BUILDING-Rough-Frame | 8/15/2023 | Corrections Issued | ALEXANDER HANDY |
| Rough-Elec/Plmb/HVAC | 8/22/2023 | Approved | HORACE FULTZ |
| Insulation | 8/29/2023 | Corrections Issued | ALEXANDER HANDY |
| Insulation | 9/5/2023 | Approved | JEFFREY PARD |
| Drywall Nailing | 9/8/2023 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 9/8/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 9/14/2023 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 10/16/2023 | Approved | ALEXANDER HANDY |
| Sewer | 10/25/2023 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 10/25/2023 | Corrections Issued | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 12/19/2023 | Corrections Issued | MORRIS JACKSON |
| Final | 12/19/2023 | Corrections Issued | MORRIS JACKSON |
| Green Building Final | 12/19/2023 | Approved | MORRIS JACKSON |
| Green Building Rough | 12/19/2023 | Approved | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 12/19/2023 | SGSOV Approved | MORRIS JACKSON |
| Smoke Detectors | 12/19/2023 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 1/2/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Final | 1/2/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Service/Power Release | 1/2/2024 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 1/25/2024 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 1/25/2024 | Approved | ALEXANDER HANDY |
| Final | 1/25/2024 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 1/25/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 1/25/2024 | Approved | ALEXANDER HANDY |