6636 N BEVIS AVE 91405

Certificate Information: 6636 N BEVIS AVE 91405

Application / Permit
22014-20000-05465
Plan Check / Job No.
B22VN16466
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE ENTIRE SFD EXCEPT 27.33LF NORTH WALL & 18LF WEST WALL AND ADD 1-STORY SFD (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 7/31/2024
Issuing Office
Current Status
CofO Issued on 3/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2022 APPLICANT
Assigned to Plan Check Engineer 11/9/2022 NILOOFAR MEHRAIN
Corrections Issued 11/15/2022 NILOOFAR MEHRAIN
Quality Review Completed 11/18/2022 STEVEN KIM
Quality Review Completed 11/18/2022 STEVEN KIM
Building Plans Picked Up 11/22/2022 APPLICANT
Applicant returned to address corrections 3/5/2024 NILOOFAR MEHRAIN
Plan Check Approved 7/25/2024 NILOOFAR MEHRAIN
Issued 7/31/2024 APPLICANT
CofO in Progress 3/12/2026 VINCENT HANLEY
CofO Issued 3/26/2026 RUBEN SALAS
Permit Finaled 3/26/2026 RUBEN SALAS

Permit Application Clearance Information

Sewer availability Cleared 12/8/2022 LUCIA MERCADO
Eng Process Fee Ord 176,300 Cleared 1/25/2023 LUCIA MERCADO
Hydrant and Access approval Cleared 6/6/2023 MATTHEW CRAIG
Low Impact Development Cleared 12/18/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 2/7/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Zelada,, Mynor Anibal; Lic. No.: C48666 22634 SYLVAN ST      WOODLAND HILLS, CA 91367

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/16/2024 Approved RYAN SALAZAR
Pre-Inspection 8/28/2024 Corrections Issued RYAN SALAZAR
Footing/Foundation/Slab 9/26/2024 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 10/11/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 10/25/2024 Partial Approval RYAN SALAZAR
PLUMBING-Rough 10/25/2024 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 10/28/2024 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Partial Approval RYAN SALAZAR
Green Building Rough 12/4/2024 Not Ready for Inspection RYAN SALAZAR
Wood Frame 12/4/2024 Not Ready for Inspection RYAN SALAZAR
Deputy Drilled-In Anchors 12/9/2024 Conditional Approval RAUL OLAGI
PLUMBING-Rough 12/12/2024 Partial Approval RYAN SALAZAR
Sewer 12/12/2024 Approved RYAN SALAZAR
ELECTRICAL-Rough 1/3/2025 Not Ready for Inspection DAVID MATSON
HVAC-Rough 1/3/2025 Corrections Issued DAVID MATSON
Rough-Elec/Plmb/HVAC 1/3/2025 Not Ready for Inspection DAVID MATSON
Underground Mechanical 1/3/2025 Partial Approval DAVID MATSON
Wood Frame 1/3/2025 Not Ready for Inspection DAVID MATSON
ELECTRICAL-Rough 1/8/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Wood Frame 1/8/2025 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/10/2025 Approved RYAN SALAZAR
ELECTRICAL-Rough 1/10/2025 Approved RYAN SALAZAR
Green Building Rough 1/10/2025 Approved RYAN SALAZAR
HVAC-Rough 1/10/2025 Approved RYAN SALAZAR
Insulation 1/15/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 1/16/2025 Partial Approval RYAN SALAZAR
Drywall Nailing 1/22/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 2/3/2025 Approved GAREN HAYRAPETYAN
Service/Power Release 5/9/2025 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Final 5/21/2025 Approved RYAN SALAZAR
Service/Power Release 5/21/2025 Approved RYAN SALAZAR
PLUMBING-Final 8/1/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 11/4/2025 SGSOV Not Ready RYAN SALAZAR
Final 12/12/2025 Corrections Issued RYAN SALAZAR
Green Building Final 12/12/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 12/12/2025 SGSOV Approved RYAN SALAZAR
Smoke Detectors 12/12/2025 Approved RYAN SALAZAR
Deputy Drilled-In Anchors 2/20/2026 Approved MICHAEL CORTEZ
Special/Order Compliance 2/23/2026 Corrections Issued JOSE AVILA
Special/Order Compliance 2/23/2026 Corrections Issued MICHAEL CORTEZ
Final 3/11/2026 OK to Issue CofO VINCENT HANLEY
HVAC-Final 3/11/2026 Approved VINCENT HANLEY
PLUMBING-Final 3/11/2026 Approved VINCENT HANLEY