5411 N BURNET AVE 91411
Certificate Information: 5411 N BURNET AVE 91411
- Application / Permit
- 22014-20000-05464
- Plan Check / Job No.
- B22VN16464
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- IRREGULAR SHAPE ADDITION TO (E) SFD. ADDITION TO RELOCATE GARAGE AND CONVERT (E) GARAGE SPACE TO SFD. (N) FRONT PORCH AND REMODEL SFD.
- Permit Issued
- Issued on 2/7/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2022 | ISIS ARGUETA |
| Corrections Issued | 11/7/2022 | ISIS ARGUETA |
| Building Plans Picked Up | 11/21/2022 | APPLICANT |
| Plan Check Approved | 1/31/2024 | SERGIO MUNIZ |
| Issued | 2/7/2024 | APPLICANT |
| CofO in Progress | 7/7/2025 | JACK KARGODORIAN |
| Permit Finaled | 7/25/2025 | RUBEN SALAS |
| CofO Issued | 7/25/2025 | RUBEN SALAS |
| Permit Finaled | 7/25/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2024 | COLIN LOREDO |
| Low Impact Development (LID) | Cleared | 1/29/2024 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 1/29/2024 | COLIN LOREDO |
| Sewer availability | Cleared | 1/29/2024 | COLIN LOREDO |
Contact Information
| Architect | Gilliam,, Jonathan; Lic. No.: C33995 | 15017 ARCHWOOD STREET VAN NUYS, CA 91405 |
| Contractor | La Top Builders Inc; Lic. No.: 1077576-B | 20701 EXHIBIT PLACE WOODLAND HILLS, CA 91367 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/6/2024 | Corrections Issued | THOMAS FINNILA |
| METHANE-Barrier | 3/6/2024 | Not Ready for Inspection | THOMAS FINNILA |
| METHANE-Subgrade | 3/6/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 3/8/2024 | Not Ready for Inspection | THOMAS FINNILA |
| METHANE-Barrier | 3/8/2024 | Not Ready for Inspection | THOMAS FINNILA |
| METHANE-Subgrade | 3/8/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 3/12/2024 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 4/3/2024 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 4/8/2024 | Partial Approval | THOMAS FINNILA |
| Drywall Nailing | 6/3/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2024 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Rough | 6/13/2024 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2024 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Rough | 6/13/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 6/13/2024 | Approved | JACK KARGODORIAN |
| Underground Mechanical | 6/13/2024 | Approved | JACK KARGODORIAN |
| Wood Frame | 6/13/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2024 | Not Ready for Inspection | RUBEN SALAS |
| Wood Frame | 6/24/2024 | Corrections Issued | RUBEN SALAS |
| Deputy Wood Construction | 6/26/2024 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2024 | Partial Approval | VINCENT HANLEY |
| Wood Frame | 6/27/2024 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 7/9/2024 | Partial Approval | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/9/2024 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 7/12/2024 | Approved | RYAN SALAZAR |
| Green Building Rough | 7/12/2024 | Approved | RYAN SALAZAR |
| Insulation | 7/12/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/12/2024 | Approved | RYAN SALAZAR |
| METHANE-Rough | 7/12/2024 | Approved | RYAN SALAZAR |
| Drywall Nailing | 7/25/2024 | Approved | JACK KARGODORIAN |
| Final | 7/1/2025 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 7/1/2025 | Approved | JACK KARGODORIAN |
| Green Building Final | 7/1/2025 | Approved | JACK KARGODORIAN |
| METHANE-Barrier | 7/1/2025 | Approved | JACK KARGODORIAN |
| METHANE-Subgrade | 7/1/2025 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 7/1/2025 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 7/1/2025 | Approved | JACK KARGODORIAN |
| Final | 7/3/2025 | OK to Issue CofO | JACK KARGODORIAN |