4014 1/2-4016 S TRINITY ST 90011

Certificate Information: 4014 1/2-4016 S TRINITY ST 90011

Application / Permit
22014-20000-05459
Plan Check / Job No.
B22VN16452
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD EXTERIOR STAIRS AND CONVERT 2ND FLOOR OF (E) SFD TO ACCESSORY DWELLING UNIT (950 SQ FT) PER GCS 66323(a)(1)
Permit Issued
Issued on 3/6/2025
Issuing Office
Current Status
Issued on 3/6/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/4/2022 APPLICANT
Assigned to Plan Check Engineer 11/14/2022 RAMA DABADGE
Corrections Issued 11/14/2022 RAMA DABADGE
Building Plans Picked Up 11/16/2022 APPLICANT
Applicant returned to address corrections 2/28/2025 JEROME MAGAT PALMA
Plan Check Approved 3/6/2025 YAQUB MIRZA
Issued 3/6/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/17/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 1/11/2023 WALLIE JONG
Sewer availability Cleared 1/11/2023 WALLIE JONG
Tenant Habitability Plan Cleared 2/25/2025 RICARDO BOHORQUEZ
ZI Cleared 2/26/2025 NATHAN ROMINE

Contact Information

Contractor Owner-Builder       ,
Engineer Kator,, Khaled; Lic. No.: C69781 19519 TULSA ST      NORTHRIDGE, CA 91326

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/10/2025 Corrections Issued MICHAEL LEWIS
Wood Frame 3/19/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/30/2025 Corrections Issued LUIS CASTRO
HVAC-Rough 4/30/2025 Corrections Issued LUIS CASTRO
Insulation 4/30/2025 Corrections Issued LUIS CASTRO
PLUMBING-Rough 4/30/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 5/5/2025 Approved BRENDAN MORELLI
Green Building Rough 5/5/2025 Approved BRENDAN MORELLI
Insulation 5/5/2025 Approved BRENDAN MORELLI
Rough-Elec/Plmb/HVAC 5/5/2025 Approved BRENDAN MORELLI
Drywall Nailing 5/15/2025 Approved ANTHONY RAMOS
ELECTRICAL-Final 6/23/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 6/23/2025 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 6/23/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 6/23/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 6/23/2025 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 12/8/2025 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 12/8/2025 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 12/31/2025 Approved OSVALDO PARAMO
Insulation 2/10/2026 Corrections Issued ALEJANDRO DE ARTOLA
Final 4/3/2026 Conditional Approval JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 4/3/2026 SGSOV Approved JOHN QUINTANILLA
Smoke Detectors 4/3/2026 Approved JOHN QUINTANILLA
Service/Power Release 5/7/2026 Approved JOHN QUINTANILLA