9322 N LA SHELL DR 91042
Certificate Information: 9322 N LA SHELL DR 91042
- Application / Permit
- 22014-20000-05442
- Plan Check / Job No.
- B22VN16385
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL, 21'-2" X 12'-0" ADDITION TO (E) SFD.
- Permit Issued
- Issued on 3/23/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 11/5/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 11/8/2022 | APPLICANT |
| Applicant returned to address corrections | 3/2/2023 | HAYATO TSUCHIYA |
| Plan Check Approved | 3/23/2023 | ALEC MOUSAKHANIAN |
| Issued | 3/23/2023 | APPLICANT |
| CofO in Progress | 8/14/2023 | DAVID ANDERSON |
| Permit Finaled | 9/6/2023 | RUBEN SALAS |
| CofO Issued | 9/6/2023 | RUBEN SALAS |
| Permit Finaled | 9/6/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2023 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 3/6/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 3/6/2023 | DAGOVERTO GUERRERO |
| ZA Case | Cleared | 3/6/2023 | ASHLEY RODARTE |
| Grading Pre-Inspection | Cleared | 3/9/2023 | KIRK LINKLATER |
| Specific Plan | Cleared | 3/22/2023 | CECILIA CASTILLO |
| ZI | Cleared | 3/22/2023 | CECILIA CASTILLO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Evangelista,, Gil Viernes; Lic. No.: S2422 | 749 N FEATHERWOOD DR DIAMOND BAR, CA 91765 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/17/2023 | Conditional Approval | MICHAEL SMITH |
| PLUMBING-Rough | 4/20/2023 | Partial Approval | DAVID ANDERSON |
| Footing/Foundation/Slab | 4/24/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 5/25/2023 | Corrections Issued | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2023 | Corrections Issued | DAVID ANDERSON |
| Green Building Rough | 5/25/2023 | Not Ready for Inspection | DAVID ANDERSON |
| HVAC-Rough | 5/25/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 5/25/2023 | Approved | DAVID ANDERSON |
| Deputy Drilled-In Anchors | 5/26/2023 | Conditional Approval | DAVID MATSON |
| Deputy Wood Construction | 5/30/2023 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 5/31/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 5/31/2023 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 5/31/2023 | Approved | DAVID ANDERSON |
| Insulation | 6/5/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 6/5/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 6/8/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Final | 8/2/2023 | Approved | DAVID MATSON |
| Final | 8/2/2023 | OK to Issue CofO | DAVID MATSON |
| Green Building Final | 8/2/2023 | Approved | DAVID MATSON |
| HVAC-Final | 8/2/2023 | Approved | DAVID MATSON |
| PLUMBING-Final | 8/2/2023 | Approved | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 8/2/2023 | SGSOV Approved | DAVID MATSON |
| Smoke Detectors | 8/2/2023 | Approved | DAVID MATSON |