12746-12748 W ALBERS ST 91607
Certificate Information: 12746-12748 W ALBERS ST 91607
- Application / Permit
- 22014-20000-05415
- Plan Check / Job No.
- B22VN16310
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- COMBINE LOT 1 AND 17 INTO ONE LOT . (N) ALTERATION AND GROUND FLOOR ADDITION TO (E) TWO STORY SFD WITH ATTACHED TWO CAR GARAGE (SFD LOCATED ON LOT 1 (E) TO REMAIN) AND ATTACHED ADU ON PORTION OF LOT 17 PER LAMC 12.22 A.33 (c) AND (e) TO BECOME A TWO STORY SFD WITH TWO CAR ATTACHED AND ATTACHED ADU"COMPLY WITH DEPARTMENT ORDER effective date 07/14/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 12/4/2024
- Issuing Office
- Current Status
- CofO Issued on 5/27/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2022 | SERGIO GUTIERREZ |
| Corrections Issued | 11/8/2022 | SERGIO GUTIERREZ |
| Quality Review Completed | 11/16/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 12/15/2022 | SERGIO GUTIERREZ |
| Plan Check Approved | 11/26/2024 | SERGIO GUTIERREZ |
| Issued | 12/4/2024 | APPLICANT |
| CofO in Progress | 4/16/2026 | SCOTT SHUSTER |
| Permit Finaled | 5/27/2026 | DAVID JAMES |
| Permit Finaled | 5/27/2026 | DAVID JAMES |
| CofO Issued | 5/27/2026 | DAVID JAMES |
Permit Application Clearance Information
| Construction near power lines | Cleared | 5/24/2024 | WALTER RAMIREZ |
| Address approval | Cleared | 6/17/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 6/17/2024 | CARLOS RAMIREZ |
| Specific Plan | Cleared | 7/16/2024 | CHRISTIAN PEARSON |
| Specific Plan | Cleared | 7/16/2024 | CHRISTIAN PEARSON |
| Hydrant and Access approval | Cleared | 7/23/2024 | KURT CORRAL |
| Low Impact Development | Cleared | 9/3/2024 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 9/5/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Yay Construction Inc; Lic. No.: 1078903-B | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/6/2024 | Partial Inspection | JOSE RUBIO |
| Pre-Inspection | 12/19/2024 | Partial Inspection | JOSE RUBIO |
| Footing/Foundation/Slab | 1/28/2025 | Partial Inspection | JOSE RUBIO |
| Deputy Drilled-In Anchors | 2/20/2025 | Approved | JOSE RUBIO |
| Excavation/Setback/Form/Re-Bar | 2/24/2025 | Not Ready for Inspection | JOSE RUBIO |
| Deputy Drilled-In Anchors | 3/4/2025 | Conditional Approval | JOSE RUBIO |
| Footing/Foundation/Slab | 3/6/2025 | Partial Inspection | SCOTT SHUSTER |
| Deputy Drilled-In Anchors | 3/17/2025 | Conditional Approval | SCOTT SHUSTER |
| Footing/Foundation/Slab | 3/17/2025 | Partial Approval | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 4/10/2025 | Partial Inspection | JOSE RUBIO |
| ELECTRICAL-Rough | 4/10/2025 | Partial Inspection | JOSE RUBIO |
| Green Building Rough | 4/10/2025 | Approved | JOSE RUBIO |
| PLUMBING-Rough | 4/10/2025 | Partial Inspection | JOSE RUBIO |
| Wood Frame | 6/6/2025 | Partial Inspection | JOSE RUBIO |
| ELECTRICAL-Rough | 6/18/2025 | Partial Inspection | JOSE RUBIO |
| PLUMBING-Rough | 6/18/2025 | Partial Inspection | JOSE RUBIO |
| BUILDING-Rough-Frame | 6/24/2025 | Partial Inspection | JOSE RUBIO |
| PLUMBING-Rough | 6/24/2025 | Not Ready for Inspection | JOSE RUBIO |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2025 | Partial Approval | THOMAS WOODS |
| HVAC-Rough | 6/30/2025 | Approved | THOMAS WOODS |
| PLUMBING-Rough | 6/30/2025 | Partial Approval | THOMAS WOODS |
| ELECTRICAL-Rough | 7/9/2025 | Partial Approval | SCOTT SHUSTER |
| HVAC-Rough | 7/9/2025 | Partial Approval | SCOTT SHUSTER |
| PLUMBING-Rough | 7/9/2025 | Approved | SCOTT SHUSTER |
| Interior/Exterior Lathing | 7/11/2025 | Not Ready for Inspection | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 7/15/2025 | Partial Approval | SCOTT SHUSTER |
| Shower Pan | 7/15/2025 | Not Ready for Inspection | SCOTT SHUSTER |
| Wood Frame | 7/15/2025 | Partial Approval | SCOTT SHUSTER |
| Insulation | 7/17/2025 | Partial Approval | SCOTT SHUSTER |
| Interior/Exterior Lathing | 7/17/2025 | Not Ready for Inspection | SCOTT SHUSTER |
| Shower Pan | 7/17/2025 | Approved | SCOTT SHUSTER |
| Drywall Nailing | 8/4/2025 | Partial Approval | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 11/4/2025 | Partial Inspection | SCOTT SHUSTER |
| Final | 11/4/2025 | Partial Inspection | SCOTT SHUSTER |
| Footing/Foundation/Slab | 11/4/2025 | Approved | SCOTT SHUSTER |
| Green Building Final | 11/4/2025 | Partial Inspection | SCOTT SHUSTER |
| SGSOV-Seismic Gas S/O Valve | 11/4/2025 | SGSOV Approved | SCOTT SHUSTER |
| Smoke Detectors | 11/4/2025 | Partial Inspection | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 11/7/2025 | Partial Inspection | SCOTT SHUSTER |
| Final | 11/7/2025 | Partial Inspection | SCOTT SHUSTER |
| Green Building Final | 11/7/2025 | Approved | SCOTT SHUSTER |
| Smoke Detectors | 11/7/2025 | Approved | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 1/30/2026 | Partial Inspection | SCOTT SHUSTER |
| Final | 1/30/2026 | Partial Inspection | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 4/16/2026 | Approved | SCOTT SHUSTER |
| Final | 4/16/2026 | OK to Issue CofO | SCOTT SHUSTER |