6313 N ATOLL AVE 91401

Certificate Information: 6313 N ATOLL AVE 91401

Application / Permit
22014-20000-05410
Plan Check / Job No.
B22VN16282
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 15' 9" X 33' 6" ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING TO ADD MASTER BEDROOM, BATHROOM, CLOSET & LAUNDRY. ALL WORK DONE PER ENGINEERING. "COMPLY WITH DEPARTMENT ORDER effective date 10/13/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 1/20/2023
Issuing Office
Current Status
CofO Issued on 11/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2022 APPLICANT
Assigned to Plan Check Engineer 11/4/2022 RAMA DABADGE
Corrections Issued 11/7/2022 RAMA DABADGE
Building Plans Picked Up 11/17/2022 APPLICANT
Applicant returned to address corrections 1/12/2023 MADISON ODELL
Plan Check Approved 1/18/2023 GURUNATH NESARAJAH
Issued 1/20/2023 APPLICANT
CofO in Progress 11/1/2024 JOSE RUBIO
Permit Finaled 11/18/2024 DAVID JAMES
CofO Issued 11/18/2024 DAVID JAMES
Permit Finaled 11/18/2024 DAVID JAMES

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/28/2022 MEGAN GODINEZ
Low Impact Development Cleared 1/9/2023 DEBORA LEITE
Roof/Waste drainage to street Cleared 1/9/2023 COLIN LOREDO
Waste Hauler Permit Cleared 1/12/2023 KENNETH BROWNE

Contact Information

Architect Miller,, Michael; Lic. No.: C26956 12756 MITCHELL AVE      LOS ANGELES, CA 90066
Contractor Owner-Builder       ,

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIO CUEVAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/29/2023 Partial Inspection BRYAN MEYER
Deputy Drilled-In Anchors 4/25/2023 Approved BRYAN MEYER
PLUMBING-Rough 4/26/2023 Not Ready for Inspection BRYAN MEYER
Sewer 4/26/2023 Not Ready for Inspection BRYAN MEYER
Footing/Foundation/Slab 5/9/2023 Corrections Issued BRYAN MEYER
PLUMBING-Rough 5/9/2023 Partial Approval BRYAN MEYER
Sewer 5/9/2023 Partial Approval BRYAN MEYER
PLUMBING-Rough 5/11/2023 Approved BRYAN MEYER
Sewer 5/11/2023 Partial Approval SCOTT SHUSTER
BUILDING-Rough-Frame 8/8/2023 Not Ready for Inspection BRYAN MEYER
ELECTRICAL-Rough 8/8/2023 Not Ready for Inspection BRYAN MEYER
Green Building Rough 8/8/2023 Not Ready for Inspection BRYAN MEYER
PLUMBING-Rough 8/8/2023 Not Ready for Inspection BRYAN MEYER
Wood Frame 8/8/2023 Not Ready for Inspection BRYAN MEYER
BUILDING-Rough-Frame 9/14/2023 Partial Inspection BRYAN MEYER
ELECTRICAL-Rough 9/14/2023 Partial Inspection BRYAN MEYER
Green Building Rough 9/14/2023 Approved BRYAN MEYER
HVAC-Rough 9/14/2023 Partial Inspection BRYAN MEYER
PLUMBING-Rough 9/14/2023 Partial Inspection BRYAN MEYER
Rough-Elec/Plmb/HVAC 9/14/2023 Partial Inspection BRYAN MEYER
Wood Frame 9/14/2023 Partial Inspection BRYAN MEYER
ELECTRICAL-Rough 10/11/2023 Partial Approval SCOTT SHUSTER
HVAC-Rough 10/11/2023 Partial Approval SCOTT SHUSTER
Interior/Exterior Lathing 10/11/2023 Partial Approval SCOTT SHUSTER
PLUMBING-Rough 10/11/2023 Partial Inspection SCOTT SHUSTER
Wood Frame 10/11/2023 Partial Approval SCOTT SHUSTER
Interior/Exterior Lathing 10/12/2023 Approved SCOTT SHUSTER
ELECTRICAL-Rough 10/27/2023 Approved SCOTT SHUSTER
HVAC-Rough 10/27/2023 Approved SCOTT SHUSTER
Insulation 10/27/2023 Approved SCOTT SHUSTER
Interior/Exterior Lathing 10/27/2023 Not Ready for Inspection SCOTT SHUSTER
PLUMBING-Rough 10/27/2023 Approved SCOTT SHUSTER
Wood Frame 10/27/2023 Approved SCOTT SHUSTER
Drywall Nailing 11/14/2023 Approved BRYAN MEYER
Shower Pan 11/27/2023 Approved BRYAN MEYER
BUILDING-Rough-Frame 3/8/2024 Approved BRYAN MEYER
Final 3/8/2024 Partial Inspection BRYAN MEYER
Footing/Foundation/Slab 3/8/2024 Approved BRYAN MEYER
Green Building Final 3/8/2024 Approved BRYAN MEYER
SGSOV-Seismic Gas S/O Valve 3/8/2024 SGSOV Not Ready BRYAN MEYER
Smoke Detectors 3/8/2024 Approved BRYAN MEYER
Final 4/4/2024 Partial Approval BRYAN MEYER
SGSOV-Seismic Gas S/O Valve 4/4/2024 SGSOV Approved BRYAN MEYER
Final 11/1/2024 OK to Issue CofO JOSE RUBIO