9670 W SOMBRA VALLEY DR 91040
Certificate Information: 9670 W SOMBRA VALLEY DR 91040
- Application / Permit
- 22014-20000-05344
- Plan Check / Job No.
- B22VN16097
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR ALTERATION TO CONSIST OF REMODELING REMODELING THROUGHOUT, REVISING THE FLOOR PLAN TO RELOCATE TWO BATHROOMS, AND AN ADDITION OF 3'8" x 6'8" ( 24.4 SQ. FT).
- Permit Issued
- Issued on 11/16/2022
- Issuing Office
- Current Status
- CofO Issued on 4/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2022 | LUIS RINCON |
| Corrections Issued | 11/1/2022 | LUIS RINCON |
| Building Plans Picked Up | 11/10/2022 | APPLICANT |
| Plan Check Approved | 11/16/2022 | HAYATO TSUCHIYA |
| Issued | 11/16/2022 | APPLICANT |
| CofO in Progress | 4/20/2023 | DAVID ANDERSON |
| CofO Issued | 4/25/2023 | MICHAEL SMITH |
| Permit Finaled | 4/25/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/10/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 11/10/2022 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 11/10/2022 | JOSE DUARTE-DIAZ |
| Public Works-Open Permits | Cleared | 11/10/2022 | JOSE DUARTE-DIAZ |
| Public Works-Sewers | Cleared | 11/10/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sayah,, Daniel H; Lic. No.: C67905 | 15233 VENTURA BLVD STE 1130 SHERMAN OAKS, CA 91403 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 12/28/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Footing/Foundation/Slab | 12/28/2022 | Partial Approval | DAVID ANDERSON |
| HVAC-Rough | 12/28/2022 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 1/10/2023 | Approved | DAVID ANDERSON |
| Footing/Foundation/Slab | 1/10/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 1/10/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 1/19/2023 | Approved | DAVID ANDERSON |
| Pre-Inspection | 1/19/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2023 | Approved | DAVID ANDERSON |
| Insulation | 1/23/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 1/31/2023 | Approved | DAVID ANDERSON |
| Shower Pan | 1/31/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 3/9/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 3/9/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 3/9/2023 | Approved | DAVID ANDERSON |
| Final | 4/19/2023 | OK to Issue CofO | DAVID ANDERSON |
| Green Building Final | 4/19/2023 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 4/19/2023 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 4/19/2023 | Approved | DAVID ANDERSON |