4841 N KLUMP AVE 91601

Certificate Information: 4841 N KLUMP AVE 91601

Application / Permit
22014-20000-05329
Plan Check / Job No.
B22VN16066
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL (E) SFD AND 6'-4" X 20'-10"ADDITION TO SFD
Permit Issued
Issued on 11/23/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2022 APPLICANT
Assigned to Plan Check Engineer 11/2/2022 JESSE ARELLANO
Corrections Issued 11/3/2022 JESSE ARELLANO
Building Plans Picked Up 11/4/2022 APPLICANT
Plan Check Approved 11/21/2022 ALEC MOUSAKHANIAN
Issued 11/23/2022 APPLICANT
CofO in Progress 4/12/2023 JACK KARGODORIAN
Permit Finaled 4/18/2023 MICHAEL SMITH
CofO Issued 4/18/2023 MICHAEL SMITH
Permit Finaled 4/18/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/10/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 11/10/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 11/10/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Spazio La Designs; Lic. No.: 1006766-B 10620 MAGNOLIA BLVD      NORTH HOLLYWOOD, CA 91601

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/16/2022 Approved THOMAS FINNILA
Footing/Foundation/Slab 12/21/2022 Conditional Approval CHRISTOPHE COCHRAN
PLUMBING-Rough 12/28/2022 Partial Approval JACK KARGODORIAN
Wood Frame 12/28/2022 Partial Approval JACK KARGODORIAN
Insulation 12/30/2022 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 1/18/2023 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 2/3/2023 Approved JACK KARGODORIAN
ELECTRICAL-Rough 2/3/2023 Approved JACK KARGODORIAN
Green Building Rough 2/3/2023 Approved JACK KARGODORIAN
HVAC-Rough 2/3/2023 Approved JACK KARGODORIAN
PLUMBING-Rough 2/3/2023 Approved JACK KARGODORIAN
Insulation 2/8/2023 Approved JACK KARGODORIAN
Interior/Exterior Lathing 2/8/2023 Partial Approval JACK KARGODORIAN
Shower Pan 2/8/2023 Approved JACK KARGODORIAN
Drywall Nailing 2/14/2023 Approved JACK KARGODORIAN
Interior/Exterior Lathing 2/14/2023 Partial Approval JACK KARGODORIAN
Final 4/10/2023 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 4/10/2023 Approved JACK KARGODORIAN
Green Building Final 4/10/2023 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 4/10/2023 SGSOV Not Ready JACK KARGODORIAN
Smoke Detectors 4/10/2023 Approved JACK KARGODORIAN
Final 4/11/2023 OK to Issue CofO JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 4/11/2023 SGSOV Approved JACK KARGODORIAN
Service/Power Release 4/11/2023 Approved JACK KARGODORIAN