16830 W LOS ALIMOS ST 91344

Certificate Information: 16830 W LOS ALIMOS ST 91344

Application / Permit
22014-20000-05304
Plan Check / Job No.
B22VN15984
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 18'-2" X 20'-0" DETACHED GARAGE WITH 9'-10" X 20'-0" ADDITION TO CONVERT TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d)
Permit Issued
Issued on 3/28/2023
Issuing Office
Current Status
CofO Issued on 4/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/7/2022 APPLICANT
Assigned to Plan Check Engineer 11/14/2022 ALEC MOUSAKHANIAN
Corrections Issued 11/15/2022 LUISANGEL VALENZUELA
Applicant returned to address corrections 12/20/2022 ALEC MOUSAKHANIAN
Plan Check Approved 3/4/2023 ALEC MOUSAKHANIAN
Issued 3/28/2023 APPLICANT
CofO in Progress 4/10/2024 JAVIER RAMOS JR
Permit Finaled 4/16/2024 RUBEN SALAS
CofO Issued 4/16/2024 RUBEN SALAS
Permit Finaled 4/16/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/16/2022 FERNANDO GIL
Roof/Waste drainage to street Cleared 11/16/2022 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 11/28/2022 FERNANDO GIL
Sewer availability Cleared 11/28/2022 FERNANDO GIL
Construction near power lines Cleared 2/11/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Hakhamaneshi,, Manouchehr; Lic. No.: C88083 12935 ALCOSTA BLVD   PO BOX 1435    SAN RAMON, CA 94583

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/1/2023 Approved JAVIER RAMOS JR
PLUMBING-Rough 10/26/2023 Partial Approval ROBERT GOLD
Deputy Drilled-In Anchors 10/30/2023 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 10/30/2023 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 11/2/2023 Partial Inspection JAVIER RAMOS JR
Sewer 11/2/2023 Approved JAVIER RAMOS JR
Underground Mechanical 11/2/2023 Partial Approval JAVIER RAMOS JR
Deputy Wood Construction 11/9/2023 Conditional Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 11/14/2023 Partial Approval JAVIER RAMOS JR
Shower Pan 11/14/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 12/4/2023 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 12/4/2023 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 12/4/2023 Approved JAVIER RAMOS JR
Green Building Rough 12/4/2023 Approved JAVIER RAMOS JR
HVAC-Rough 12/4/2023 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 12/4/2023 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 12/4/2023 Approved JAVIER RAMOS JR
Underground Mechanical 12/4/2023 Approved JAVIER RAMOS JR
HVAC-Rough 12/7/2023 Approved JAVIER RAMOS JR
Insulation 12/7/2023 Approved JAVIER RAMOS JR
Drywall Nailing 12/11/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 12/14/2023 Approved JAVIER RAMOS JR
Pre-Inspection 12/14/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 1/10/2024 No Access for Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 4/2/2024 Approved KEVIN BERBERYAN
Final 4/2/2024 Corrections Issued KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 4/2/2024 SGSOV Not Ready KEVIN BERBERYAN
Service/Power Release 4/2/2024 Approved KEVIN BERBERYAN
Smoke Detectors 4/2/2024 Approved KEVIN BERBERYAN
Final 4/4/2024 Partial Approval JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 4/4/2024 SGSOV Approved JAVIER RAMOS JR
Final 4/10/2024 OK to Issue CofO JAVIER RAMOS JR