16830 W LOS ALIMOS ST 91344
Certificate Information: 16830 W LOS ALIMOS ST 91344
- Application / Permit
- 22014-20000-05304
- Plan Check / Job No.
- B22VN15984
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 18'-2" X 20'-0" DETACHED GARAGE WITH 9'-10" X 20'-0" ADDITION TO CONVERT TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d)
- Permit Issued
- Issued on 3/28/2023
- Issuing Office
- Current Status
- CofO Issued on 4/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2022 | ALEC MOUSAKHANIAN |
| Corrections Issued | 11/15/2022 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 12/20/2022 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 3/4/2023 | ALEC MOUSAKHANIAN |
| Issued | 3/28/2023 | APPLICANT |
| CofO in Progress | 4/10/2024 | JAVIER RAMOS JR |
| Permit Finaled | 4/16/2024 | RUBEN SALAS |
| CofO Issued | 4/16/2024 | RUBEN SALAS |
| Permit Finaled | 4/16/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/16/2022 | FERNANDO GIL |
| Roof/Waste drainage to street | Cleared | 11/16/2022 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 11/28/2022 | FERNANDO GIL |
| Sewer availability | Cleared | 11/28/2022 | FERNANDO GIL |
| Construction near power lines | Cleared | 2/11/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hakhamaneshi,, Manouchehr; Lic. No.: C88083 | 12935 ALCOSTA BLVD PO BOX 1435 SAN RAMON, CA 94583 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/1/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 10/26/2023 | Partial Approval | ROBERT GOLD |
| Deputy Drilled-In Anchors | 10/30/2023 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 10/30/2023 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 11/2/2023 | Partial Inspection | JAVIER RAMOS JR |
| Sewer | 11/2/2023 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 11/2/2023 | Partial Approval | JAVIER RAMOS JR |
| Deputy Wood Construction | 11/9/2023 | Conditional Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 11/14/2023 | Partial Approval | JAVIER RAMOS JR |
| Shower Pan | 11/14/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 12/4/2023 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 12/4/2023 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 12/4/2023 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 12/4/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 12/4/2023 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 12/4/2023 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 12/4/2023 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 12/4/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 12/7/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 12/7/2023 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 12/11/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 12/14/2023 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 12/14/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 1/10/2024 | No Access for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/2/2024 | Approved | KEVIN BERBERYAN |
| Final | 4/2/2024 | Corrections Issued | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 4/2/2024 | SGSOV Not Ready | KEVIN BERBERYAN |
| Service/Power Release | 4/2/2024 | Approved | KEVIN BERBERYAN |
| Smoke Detectors | 4/2/2024 | Approved | KEVIN BERBERYAN |
| Final | 4/4/2024 | Partial Approval | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 4/4/2024 | SGSOV Approved | JAVIER RAMOS JR |
| Final | 4/10/2024 | OK to Issue CofO | JAVIER RAMOS JR |