8414 N SHOUP AVE 91304

Certificate Information: 8414 N SHOUP AVE 91304

Application / Permit
22014-20000-05279
Plan Check / Job No.
B22VN15921
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 21' X 21' TO & CONVERT (E) 21' X 21' DETACHED GARAGE TO ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A. 33(C) AND (D), NFPA-13D FIRE SPRINKLERS REQUIRED THOUGHOUT., ALL WORK PER ENGINEERING
Permit Issued
Issued on 8/2/2023
Issuing Office
Valley
Current Status
CofO Issued on 10/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/25/2022 APPLICANT
Assigned to Plan Check Engineer 11/17/2022 RARES BODEA
Corrections Issued 11/22/2022 RARES BODEA
Quality Review Completed 12/6/2022 STEVEN KIM
Building Plans Picked Up 12/7/2022 APPLICANT
Plan Check Approved 2/21/2023 RARES BODEA
Issued 8/2/2023 APPLICANT
CofO in Progress 10/8/2024 CHRIS CHRISTENSEN
Permit Finaled 10/17/2024 JOHN JANSON
CofO Issued 10/17/2024 JOHN JANSON
Permit Finaled 10/17/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/8/2022 FERNANDO GIL
BHO/Hillside ordinance Cleared 12/8/2022 FERNANDO GIL
BHO/Hillside ordinance Cleared 12/8/2022 FERNANDO GIL
BHO/Hillside ordinance Cleared 12/8/2022 FERNANDO GIL
BHO/Hillside ordinance Cleared 12/8/2022 FERNANDO GIL
BHO/Hillside ordinance Cleared 12/8/2022 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 12/8/2022 FERNANDO GIL
Roof/Waste drainage to street Cleared 12/8/2022 FERNANDO GIL
Sewer availability Cleared 12/8/2022 FERNANDO GIL
Street Frontage Cleared 12/8/2022 FERNANDO GIL
Distance to fire station Cleared 2/10/2023 GILBERT URREA

Contact Information

Contractor Owner-Builder       ,
Engineer Chatsky,, German; Lic. No.: C84153 3876 HUNTERS GROVE CT      MOORPARK, CA 93021

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/10/2023 Corrections Issued MORRIS JACKSON
Underground Mechanical 8/22/2023 Partial Approval JEFFREY HARTLINE
Underground Mechanical 8/25/2023 Approved JEFFREY HARTLINE
Footing/Foundation/Slab 9/15/2023 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 12/19/2023 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 12/19/2023 Approved JEFFREY HARTLINE
Green Building Rough 12/19/2023 Approved JEFFREY HARTLINE
HVAC-Rough 12/19/2023 Approved JEFFREY HARTLINE
PLUMBING-Rough 12/19/2023 Approved JEFFREY HARTLINE
Sewer 12/19/2023 Approved JEFFREY HARTLINE
Verify Sprinkler Sign Off 12/19/2023 Approved JEFFREY HARTLINE
Drywall Nailing 9/4/2024 Approved JEFFREY HARTLINE
Final 9/4/2024 Not Ready for Inspection JEFFREY HARTLINE
Green Building Final 9/4/2024 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 9/4/2024 SGSOV Not Ready JEFFREY HARTLINE
Smoke Detectors 9/4/2024 Approved JEFFREY HARTLINE
Final 10/7/2024 OK to Issue CofO CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 10/7/2024 SGSOV Approved CHRIS CHRISTENSEN